|

Contents:
Controversy continues over second high
school site; Board proceeds with ballot measure
Woodmoor residents discuss plans for
second high school
Monument Board of Trustees,
August 7: Financing of new town police building
approved
Monument Board of Trustees,
August 21: Open house held on Baptist Road
interchange plans
Monument Planning Commission,
August 9: Promontory Pointe plans recommended for
approval
Baptist Road Rural
Transportation Authority, August 11: Draft
language for sales tax discussed
Baptist Road Rural
Transportation Authority, August 28: Sales tax
ballot question certified
Palmer Lake Town Council Workshop,
August 3: All agenda items continued due to
applicants’ absences
Palmer Lake Town Council Meeting,
August 10: Fire Authority proposes new support
agreement
Palmer Lake Planning Commission,
August 16: Three proposals recommended for approval
Donala Water and Sanitation
District, August 21: Area water groups work to find
supplemental water sources
Forest View Acres Water District,
August 24: Board places property tax measure on the
November ballot
Monument Sanitation District, August
15: Office upgrade nearing completion
Tri-Lakes Wastewater Treatment
Facility Open House, August 12: Facility shows off
new capabilities
Triview Metropolitan District,
August 23: District considers loan allocations
Triview Metropolitan District,
August 30: Board approves ballot measure
Triview Ballot Issue
Woodmoor Water and Sanitation
District, August 10: District will serve new high
school
Donald Wescott Fire Protection
District, August 16: Board renews insurance policy
with VFIS
Tri-Lakes Fire Protection District,
August 24: New ambulance on the way
Woodmoor/Monument Fire Protection
District, August 23: Firefighters praised for work
on Station 3 remodel
Tri-Lakes-Monument Fire Authority,
August 23: Auditors expenses questioned
Fox Run Regional Park master
plan update open house, August 29: Park plan
receives favorable comments
Woodmoor Improvement Association
Board, August 16: Board approves matching funds for
fire protection grants
August Weather Wrap
Letters to Our Community
-
Between The Covers at the Covered
Treasures Bookstore: Page turners
-
High Country Highlights: To
Deadhead or Not to Deadhead
-
Reflections: A
Care Bear Color Wheel
-
Bird Watch on the Palmer Divide: Yellow
Warblers
-
Art Matters:
It pays to collect art
-
Over the Bar
performs for the Black Rose Acoustic Society, Aug. 25
-
Special Events and Notices
the PDF file.
This is a 15.5 Mbyte file and will take about 90 minutes
to download at 28.8. To view and print the file, you will need to download
and install the free Acrobat Reader Program.

Controversy continues over second high
school site; Board proceeds with ballot measure
Below: Resident Jim Forman expresses concern about the
traffic flow. Photo by John Heiser

Below: Hunter Run Farm, 40 acres of the 69 acres under
contract by D-38 as the site for the second high school. Photo by Jim
Kendrick

By John Heiser
At the Lewis-Palmer District 38 School Board meeting August
17, the board unanimously voted to proceed with two measures for the November
ballot. If approved by voters, the measures would authorize an increase in
property taxes of $2 million per year starting in 2008 and authorize the
district to issue up to $57 million in additional debt to pay for construction
and operation of the second high school and to make improvements to Lewis-Palmer
High School.
Terry Casey, the district’s bond advisor, estimated that
the tax impact of both questions would be approximately $35 per year on a house
valued at $315,000, the average market value of houses in the district. Casey
noted that depending on the future growth rate of the district, the bonds might
have to be issued incrementally.
Although the ballot measure does not mention the specific
site of the second high school, the board’s resolution approving the wording
of the ballot measure identifies the site as "approximately 69 acres of
land referred to as the ‘Hunter’s Run Property’ and parcels adjacent
thereto…." That site lies north of Lewis-Palmer Middle School between
Woodmoor Drive and Monument Hill Road. The resolution and ballot questions are
posted at www.lewispalmer.org.
Seven residents spoke against the board’s decision to use
that site. One person spoke in favor.
The issues raised by the opponents included the effect of the
traffic from the second high school on the surrounding roads and the increased
risk to students at Lewis-Palmer Middle School; noise, air pollution, and HazMat
and crash hazards due to the proximity of the site to I-25; the number of
schools in that area; skepticism about the results of the district’s growth
study; and concerns about increased fire risk and crime. Resident Jim Forman
said, "No due diligence was done, especially regarding the traffic."
He noted that Monument Hill Road is a narrow, two-lane frontage road to I-25
that lacks shoulders and sidewalks. He added that the traffic from three schools
would be concentrated on Woodmoor Drive. Larry Goade described the board’s
action in contracting for the site, before all of the issues had been addressed
with the community, as, "Fire, ready, aim."
Ian Griffis, who was accompanied at the podium by his
daughter Haley, spoke in favor of the new site and commended the board for
listening to the community. Griffis, who served as a volunteer on the search for
a new location, said, "We should support our kids. No site is without
impact. The traffic flow can be improved. I’m convinced there is no better
alternative."
The board addressed a number of other topics including:
-
Commendation for Cohn – Retiring general counsel
to the district, attorney Bob Cohn, was recognized for his service over the
past two decades.
-
Staff commendations – Dr. Keith Jacobus and Dr.
Marie Revak were recognized for their efforts in organizing New Teacher
Orientation Week. Ted Belteau was thanked for his participation in
orientation activities. Ray Blanch and Cheryl Wangeman were recognized for
their preparations for the bond and mill levy election in November.
-
Title and responsibility changes – The board
voted to approve the following new titles and responsibilities: Dr. Keith
Jacobus, executive director of Learning Services, and Ted Belteau, executive
director of Personnel Services. Dr. Laura Douglas, executive director of
Special Programs, will handle 504 plans. She and Belteau will split other
student service responsibilities. Wangeman will reconfigure the finance
office, adding an accountant and a secretary.
-
Conceptual considerations for Phase III Reconstruction
– The board authorized Superintendent Michael Pomarico to move forward
with Phase III plans for reconfiguration of services.
-
Sale of Technology Assets – Blanch noted that
$16,000-20,000 was gained this year from sales of computer equipment that is
no longer used in the district.
-
District-wide Communication Plan – Donna Wood,
public information officer, presented a draft Communication Plan for 2006-07
that she and the communication committee developed. The purpose of the plan
is to serve as a guide for maximizing the district’s effectiveness in
communicating with the public and within the district.
-
Financial Impact Procedures – Wangeman presented
a draft form to estimate the expected financial impact of requests presented
for Board approval.
-
CSAP Scores – Blanch and Dr. Revak gave an
overview of the district’s CSAP results. Blanch said, "We have some
of the most outstanding students in the state."
**********
The Lewis-Palmer District 38 Board of Education normally
meets on the third Thursday of each month at the Learning Center of the
Lewis-Palmer Administration Building, Second and Jefferson. The next meeting is
7 p.m. Sept. 21. The district’s Web site is at www.lewispalmer.org.
Meeting highlights from the Web site were used in preparing this article.
Below: (L to R) Retiring general counsel to the district,
attorney Bob Cohn, receives commendation from Ted Belteau.


Woodmoor residents discuss plans for
second high school
By Chris Pollard
About 125 Woodmoor residents gathered at Lewis-Palmer Middle
School auditorium August 7 to hear about and discuss the district’s plan for a
second high school on land between Woodmoor and Interstate 25 about a half-mile
north of the Middle School.
Hans Post, president of the Woodmoor Improvement Association,
introduced himself, several members of the WIA board who were present and the
two representatives from the school district, Gail Wilson, District 38 school
board member representing the Woodmoor area, and Ray Blanch, District 38
executive director of Research Assessment and Technology
Wilson said this would be the first of many meetings to
discuss planning for the site and that the district was trying to cover the
needs of many residents. Ray Blanch said the district wanted to continue the
partnership with the WIA over concerns about the new school in much the same way
as concerns, such as traffic safety problems, had been addressed at the current
high school.
Blanch stressed that the school district was trying to
anticipate the concerns of its neighbors and will form a design advisory group
consisting of parents, school board members, teachers and students. Although
there were no formal plans showing the position or design of the high school, it
was anticipated that the main building will be located on the northern part of
the land and the athletic fields will be in the southern part. The buildings and
athletic fields would be biased toward the west so that land could be reserved
to act as a screen from the adjacent housing. (The location of the site is shown
on the web site: lewispalmer.org)
The current goal is to provide regular vehicular access to
the school only on the north and west sides of the site from the Monument Hill
frontage road and a new four-lane road proposed within the Misty Acres
development. There might be two access points within Woodmoor, but these would
only access the athletic fields and emergency vehicles.
Clarifying this in response to a resident’s concern over
whether this siting and access were guaranteed, Blanch made it clear that
regular access from Woodmoor Drive would not be a good idea and that the
district would work with Woodmoor Public Safety on an ongoing basis to ensure
that.
In anticipation of concerns over stadium lights, he said the
school district planned to improve the original stadium at the current high
school and make that a district facility. This was the best fiscal decision,
Blanch said, and would probably mean doubling the seating capacity and changing
to a synthetic surface to accommodate the additional use. There would probably
be a practice field for JV teams at the new site.
Blanch reiterated the need to be good neighbors in the
placement of the buildings and the field, and said the district will try to
preserve as much of the site as possible with an eastern buffer zone. Heating
and cooling units will probably be hidden on top of the building, he said, and
the district will work with the civil engineers and landscape experts to build
the school into the hillside to minimize its effect on the area. A design
advisory group will be assembled to work on this issue.
To put the need for the new school in perspective, Blanch
noted that there would be 150 more high school students than there were last
year. Mobile classrooms have been doubled since last year, and to maintain its
excellent education record, the district must address the potential growth and
plan on opening a new high school in 2008. The school district saw that high
school enrollment could grow to as many as 2,000 in coming years. The district
would also like to improve access to the current high school by building an
entrance on Jackson Creek Parkway at a new intersection shared with the entrance
to the proposed YMCA facility.
To pay for this, the school board was proposing a $57 million
bond issue and a $2 million mill levy override to generate funds to operate the
building. On a typical house valued at $315,000 the yearly tax would be about
$40. This is less than the estimated $65 increase for the last bond issue
proposal because of the increased number of commercial buildings with their
corresponding assessed valuations. The board will form a campaign committee to
communicate the need for this bond issue, Blanch said.
School officials then answered questions from residents,
including the following:
Q. How will the student load be split?
A. The goal is to split the district into north and south
areas roughly along Highway 105. There may be some need for
"fudging" so that students might switch between the two to attend
different programs. They invited people to join the Facility and Enrollment
Committee to help work on these issues.
Q. How would they make sure the entrance off Woodmoor
Drive is for emergency use only?
A. This will probably be gated with some form of access
control.
Q. Looking at the northern El Paso County transportation
plan, it seemed as though the frontage road would disappear as part of the
widening of I-25.
A. This road is currently owned by CDOT and will be
transferring to El Paso County ownership. Discussions with County Commissioner
Wayne Williams did not indicate any proposals to eliminate it.
Q. How will they address the issue of traffic on Deer
Creek Road from the Charter School?
A. The school board has no direct authority over the
Charter School on traffic issues and there is some discussion that the school
might be moved.
Q. Has any assessment been done on traffic in the
Woodmoor area?
A. This will be an ongoing process by the traffic
engineers.
Q. Can the growth study and its effects on traffic be
released? Isn’t most of the growth to the east?
A. Yes, they will publish the study and its updates on the
website.
Q. The site selection process seems to be arbitrary. Why
weren’t local people consulted on the acceptability and selection of the
site?
A. This was a district-wide process carried out by elected
officials and many others to provide district-wide acceptance.
Q. Safety and noise are issues because of the proximity
to I-25 with its many trucks and occasional hazardous cargos.
A. The high school in Castle Rock and others around the
state are also similarly near I-25. These issues will be reviewed as part of
the safety study. They will need to talk to experts to make it as safe as
possible and also work to reduce the effect of noise.
Q. Will there be a smoking area at the new school?
A. This issue will be addressed in partnership with the
county Sheriff’s Office and Woodmoor Public Safety.
Q. Is the land under contract?
A. Yes, the school district has a contract for 69 acres and
is working on another five acres.
Q. Will road lighting be improved?
A. Yes.
Q. What will they do for residents of the land right
next to the school?
A. They will commit to making this a buffer zone. The
district will work with residents to erect any necessary fences or sound
barriers.
Q. Why was the currently owned site at the intersection
of Highways 83 and 105 not chosen? Isn’t most growth out East?
A. The site has a number of issues. The state
Transportation Department will not allow an entrance onto 83, and the site
itself is insufficient to support a high school as large as that currently
proposed. Surveys show that most growth is closer to I-25, with more
multifamily units being planned.
Q. What was the price of the land?
A. The contract terms do not allow disclosure of the price.
It will be on record after closing.
Q. Both ends of the frontage road will need improvement.
Who will do that? What if the county says that the school district needs to
pay? Why was the land bought before answering these questions?
A. El Paso County has not been involved yet. The district
will work with them to resolve the problems.
Q. Personal experience from another area indicated that
having a high school near a middle school where children have disposable
income might increase drug use there. Why place the high school near the
middle school?
A. The school board will look at this concern.
Q. Is it possible to stop the contract, and are there
contingencies in place if the bond issue doesn’t pass?
A. It would be difficult to stop the contract or to write
one with such contingencies, given the current demand for land. The bond issue
needs to pass to build another high school to address the fact that the
current high school is not large enough.
Q. Why is there the necessity to build near Woodmoor?
The current high school is adjacent to South Woodmoor and further construction
seems to be forced into this area. There is no increase in high school
students from Woodmoor.
A. The local area, unlike Castle Rock, is not a
master-planned community. There are many separate government and
non-government entities in the school district area, each with their own
plans. Land is not allocated for schools, and there are a limited number of
sites available. This school serves a much wider area than Woodmoor.
Q. Will the WIA provide security?
A. Yes, they will negotiate with the school district to
provide service.
Q. The proposed site is not flat. Will this be a
problem?
A. The civil engineers believe that it can be made to fit
with minimum disturbance of the land.
Note: In some cases, questions asked and answers given at
different times were combined.

Monument Board of Trustees, August 7: Financing
of new town police building approved
By Jim Kendrick
The Monument Board of Trustees approved lease-purchase
financing for a new police and town office building on the southwest corner of
Highway 105 and Beacon Lite Road. The board also reviewed preliminary revenue
and expenditure performance figures for 2006. Trustees Gail Drumm and Steve
Samuels were absent.
Mayor Byron Glenn said Town Manager Cathy Green had been
given discretion to use board contingency funds to arrange a luncheon and
"roast" on Aug. 23 and purchase of a gift honoring the resignation of
Triview Metropolitan District Manager Ron Simpson.
Trustee Tim Miller urged residents to vote on Aug. 8.
Jackson Creek resident Steve Meyer suggested that the town
pursue a cost-effective method for recycling similar to that initiated by
Manitou Springs for glass, tin, aluminum, and paper.
Police/Town Hall financing selection
Financial consultant Jim Manire, of James Capital Advisors
Inc., reported that the town had received three financing proposals that were
good for 30 days, with the condition that a completed environmental impact
statement would be available for the site at closing. He recommended that the
town select the 10-year lease-purchase financing proposal from Wells Fargo Bank
due to its higher flexibility on pre-payment. The Wells Fargo interest rate was
4.45 percent and allowed pre-payment without a penalty, with fees and expenses
of about $36,250. Manire also said Wells Fargo had far more experience in
Colorado tax-exempt financing, and a higher probability of being able to close
on time to lock in the proposed rate. Total interest for the full term would be
about $750,000.
The Bank of America proposal offered the same rate of 4.45
percent but no pre-payment option; fees and expenses were $10,000. The Key
Government Finance interest rate was 5.17 percent with fees and expenses of
$5,000; no pre-payment option was offered.
Green said that the 2006 budget restatement proposal should
be available at closing and that the land contract was undergoing a legal
review. Manire said closing could occur in 10-14 days, making the loan funding
available to begin construction. Green recommended scheduling a formal hearing
for approval of the loan and land contracts at the Aug. 21 board meeting.
Forest View Acres Water District inclusion requested
Stuart Currier, who lives in the Forest View Acres Water
District, asked the town to consider providing town water to the district
starting in late 2007. He said he does not "believe the board can manage
the district" due to its proposal for a November property tax mill levy
ballot initiative to upgrade inadequate and unsatisfactorily maintained
infrastructure. Currier said the proposed initial bond issue would result in a
32-mill levy for 40 years. He also said that within five years the district
plans to further increase taxes with a second bond issue. Currier noted that his
was one of nine widely separated homes that should be allowed to withdraw from
the water district because of the very high cost for the district to upgrade
service to meet current service standards. He said it would be cheaper for all
concerned if each of the nine homeowners drilled a well at a cost of about
$7,500 each.
Public Works Director Rich Landreth said he would have to
review the issues for including the district, which is not contiguous with any
town boundary other than Monument Lake’s. He also said that the district’s
senior surface-water rights in Monument Creek for 120 gallons per minute might
be useful to the town as would the district’s storage tank site. He also noted
that the district consultant’s proposed capital costs to bring the district up
to current state and federal standards exceed $6 million.
Trustee Dave Mertz asked Landreth whether other Forest View
Acres infrastructure met town standards due to the liability incurred through
annexation. Landreth said that the roads do not meet town standards. Green said
no analysis had been performed on projected upgrade costs or creating a special
separate zone that would not obligate the town to maintain infrastructure and
might also have a separate taxing structure. Miller told Currier that there is
usually opposition to any annexation proposal.
Fees for multiple land use document reviews increased
Director of Development Services Tom Kassawara recommended
charging a fee of $400 to developers for each additional staff review after the
first two reviews of site plans. Trustee Tommie Plank suggested moving the
additional reviews to "the end of the line" to penalize "their
ineptness" as an additional incentive to developers and their consultants
to respond to staff comments more efficiently. Kassawara suggested using his
discretion rather than making a new policy part of the fee structure. The new
fees were approved unanimously.
Board unanimously approves five liquor licenses
The Tri-Lakes Chamber of Commerce requested a special event
liquor permit for a beer and wine garden as part of its second annual Street
Dance at Monument Plaza on Aug. 26. Beneficiaries of the charitable event are
Tri-Lakes Cares (50 percent), as well as the Faith Community Church building
fund, the Life Academy scholarship program, and purchase of body armor for Air
Force Academy Security police dogs being deployed to the Iraq war zone.
The board unanimously approved routine one-year liquor
license renewals for Tri-Lakes Liquor, 585 Highway 105, and a 3.2 percent
beer/fermented beverage license for Safeway, 624 Highway 105. Monument Police
Department Detective Mark Owens attested that there have been no violations at
either business in the past 12 months.
Attorney Allen Dill said 7-Eleven Inc. has changed its policy
and is franchising its corporate Front Range stores but retaining joint 50-50
ownership of each store’s 3.2 percent beer/fermented beverage liquor license
with its new owner operators. The new partner for the store at 283 Highway 105
is Rajesh Chugh, of Chugh Enterprises, Inc. Though Chugh has been the operator
of the store, he attended a six-week corporate liquor license training program
as a new joint owner. Town Clerk Scott Meszaros said the application for the new
license should be processed by the state within 30 days. The temporary license
was unanimously approved.
Wal-Mart Stores, Inc. sought a new 3.2 percent beer/fermented
beverage liquor license for its Monument Marketplace Supercenter. Meszaros said
that Wal-Mart is already approved by the state, so the investigation would be
for the specific manager for this store, Angela Mitchell.
Mitchell said underage cashier employees are not allowed to
touch alcohol products that are being purchased. Instead, the store’s customer
service manager performs checkout and ID checks. Mitchell also said that even
though the requested Colorado license would permit round-the-clock liquor sales,
Wal-Mart’s policy is to suspend sales from midnight to 7 a.m. Her license was
approved unanimously.
2006 budget restatement proposed
Treasurer Pamela Smith said that the completion of the 2005
audit had finalized the specific amounts of money carried over to 2006 budget,
making these funds, along with increased 2006 revenues, available for allocation
against unexpected expenses and reduction of long-term debt. The amount carried
forward in the general fund was $222,465, and $1,423,178 was carried forward in
the Water Enterprise Fund. The total amount carried forward in all the minor
funds was $317,195, most of which is unspent funds for capital projects. Smith
said that posting requirements required the board to wait until the Sept. 21
meeting for approval of the restatement. Green added that while there might be a
pre-payment penalty for some old high-interest bond debt, there are no TABOR
restrictions on early payoffs.
Some of the proposed budget restatement recommendations were:
-
Payment of $520,000 for the land for the new Police
Department/Town Hall building.
-
Reduction of long-term debt principal by $43,000.
-
Addition of two part-time employment positions.
-
Addition of one full-time law enforcement employment
position to cover court duties.
-
Addition of one full-time position for principal planner,
while a construction inspector position replaced the staff engineer
position.
-
Addition of one full-time position in September for new
water billing clerk position.
-
Increased Police Department overtime and equipment for
replacement police vehicle.
-
Additional $50,000 for unbudgeted emergency work on town
wells.
-
Additional $45,300 for additional well expenses
-
Additional $77,000 for a well generator.
-
Additional payment of $485,689 to reduce the principal
balance on the Monument Lake Dam loan to save $523,000 in interest payments.
-
Additional $53,150 for storm drainage capital outlay.
-
Additional $227,446 for traffic capital outlay.
-
Additional $14,250 for cost of unifying town and Triview
Metropolitan District land use standards.
Two payments over $5,000 were unanimously approved:
-
$11,785 for consultant engineering work performed by GMS,
Inc. for a water treatment plant
-
$520,000 for the land purchase for the new Police
Department/Town Hall building.
Town Attorney Gary Shupp reported that it appeared that
Lewis-Palmer School District 38 would not appeal the District Court decision to
reject its lawsuit against the town.
Green reported that the town’s web site would be
unavailable during revision. An "under construction" notice will
appear when people try to log on, until the site is restructured.
The meeting adjourned at 7:50 p.m.

Monument Board of Trustees, August 21: Open
house held on Baptist Road interchange plans

Click here on the drawing below to
zoom in or download the Baptist interchange design

By Jim Kendrick
The Monument Board of Trustees (BOT) held an open house
meeting at Creekside Middle School Aug. 21 to once again discuss the
relationship between ongoing and proposed Baptist Road improvement projects.
Some of the needed Baptist Road improvements are underway east of I-25, but
there is no funding currently to improve the I-25 interchange. The meeting was a
follow-up to a similar open house session on June 19 and started early so that
several emergency ordinances could be approved prior to the Baptist Road
presentation. Trustees Tim Miller and Tommie Plank were absent.
Budget changes and police building funding approved
The board unanimously approved separate emergency ordinances
adopting a supplemental budget and corresponding appropriation. Additional
revenues from the 2005 audit were carried forward and added to the beginning
balances to the 2006 budget. These additional funds and unexpected 2006 revenues
were allocated and appropriated to new expenditures in the budget restatement
for land purchases, capital projects, and debt reduction that were discussed and
approved at the previous board meeting:
The board also unanimously approved an emergency ordinance
for lease-purchase financing (not to exceed $3.2 million) agreement with Wells
Fargo Bank for the new building for the police department and town hall offices.
The site is the southwest corner of Highway 105 and Beacon Lite Road. Green said
that the financing had to be in place before the town could issue a request for
proposal for construction of the building. She also said that the cost of the
land ($520,000 or $10 per square foot) was in line with the few other comparable
costs for nearby commercial land that were available.
(See article on Aug. 7 BOT meeting
for details)
The board unanimously approved a resolution declaring Aug. 23
"Ronald Jay Simpson Day" in recognition of his service to the town.
Simpson resigned as the manager of Triview Metropolitan District Aug. 30. He
held the post for 11 years.
Japanese citizen Akio Nyuriamo, a chaperone for Japanese 4-H
students from the region around Kyoto and Osaka who were visiting Monument,
presented Mayor Byron Glenn with several "traditional Japanese good
will" gifts to thank the town for its support of her organization’s
annual visits. Glenn thanked her and exchanged bows with her as each gift was
presented.
The board unanimously approved four payments over $5,000:
-
$47,126.85 to Triview Metro District for its share of the
town’s June sales tax revenue
-
$4,913.30 to Triview Metro District for its share of the
town’s motor vehicle specific ownership tax.
-
$13,336 to traffic consultant SHE, Inc. for professional
services.
-
$9,600.53 to Robinson Construction, LLC for restroom
construction in Dirty Woman Creek Park.
Tax initiative discussed
Mayor Glenn, Town Manager Cathy Green, PBS&J project
manager Steve Sandvik, County Commissioner Wayne Williams, and District 9
Colorado State Transportation Commissioner Terry Schooler explained the Baptist
Road Rural Transportation Authority (BRRTA) November ballot initiative for a
temporary sales tax to privately finance early improvements to the state-owned
I-25 Baptist Road interchange. Citizens asked several questions after the
presentations.
Glenn reviewed the history of BRRTA’s efforts to expedite
interchange improvements.
-
BRRTA was formed in 1997 when there were only a very few
houses (Kingswood) and two businesses (Total and Brookhart’s) within its
boundaries.
-
The interchange was a top priority project in the Pikes
Peak Area Council of Government’s (PPACG) Transportation Improvement Plan
which guides state funding of capital highway projects in 1998 and 1999 for
improvements in 2000 or 2001. However, there was only enough funding
available at that time for the I-25 Highway 105 (Exit 161) interchange
improvements.
-
After the interchange lost its highest priority ranking,
BRRTA went to the developers of the Monument Marketplace and Timbers at
Monument to seek private financing for the $16 million interchange, but the
cost was too high for them to absorb.
-
BRRTA next proposed a voluntary 3 percent public
improvement fee to be collected by Wal-Mart as a condition of approval for
construction on the southeast corner of Baptist Road and Jackson Creek
Parkway in the county, which fell through when the Board of County
Commissioners did not approve their development proposal. This parcel was
subsequently annexed by the town for the Monument Ridge community commercial
development.
-
A 1-percent public improvement fee for all commercial
entities in BRRTA was then proposed after Wal-Mart decided to open a
supercenter in the Monument Marketplace, but Wal-Mart refused to
participate, saying it was a tax that the voters should approve.
-
Commissioner Williams then proposed a ballot initiative
for a temporary 1-cent sales tax for BRRTA commercial entities to finance
the private revenue bonds used to pay for early construction of the
state-owned interchange. This taxing potential remained available to BRRTA
due to Monument choosing not to participate in the temporary one-cent sales
tax for the recently approved Pikes Peak Rural Transportation Authority.
Williams recommended against making the proposed temporary sales tax
applicable to the entire town of Monument in order to increase the
likelihood of a positive outcome, now that the Highway 105 interchange is
already completed.
-
Glenn noted that CDOT would have been unable to reimburse
BRRTA for its early construction of the Baptist Road interchange until PPACG
again declared Exit 158 a "regional priority." He said the board
had been successful in getting PPACG to redesignate the interchange the
third highest regional priority in July due to BRRTA’s approval of the
temporary one-cent sales ballot initiative, the first of three necessary
steps.
-
Glenn said the second step was an Aug. 17 CDOT resolution
stating that they would pay back BRRTA’s cost when state funds become
available, perhaps within five to ten years. Without this resolution,
funding might not be available until 2020 or later. Other major factors
leading to approval were 95 percent completion of the design of the
interchange by PBS&J and donation of land for right-of-way by developers
which has reduced the cost of the project by about $2 million.
-
The third step is voter approval of the bond issue. The
size of the revenue bond issue will be $20.0 million to $21.5 million.
Current estimates for interchange expansion are from $15.0 million to $16.5
million.
-
The bond issue is much higher than construction cost
estimates due to recent unpredictably high rates of increase (far above
inflation) in material and labor costs. There is also a need to borrow
enough extra principal to cover the shortfall in near term sales tax revenue
during the first three years of interest and principal payments until enough
additional new stores are built within the new BRRTA shopping centers to
cover the entire bond payments. The length of the temporary sales tax is 20
years or until the bonds are paid off. The bond principal would probably be
paid off much sooner than that if CDOT funding never becomes available.
-
The size and term of the bond issue are very conservative
because they are pure revenue bonds, with no physical collateral to reduce
the risk to the bond purchasers if there was not enough sales tax revenue to
pay off the bonds in 20 years and CDOT never reimbursed BRRTA. The
bondholders would lose the un-reimbursed portion of their investment in that
"unlikely" case.
-
After CDOT has made its payment to BRRTA and once all the
required financial transactions for early recall and liquidation of the
bonds are completed, the sales tax will cease. Any leftover funds from the
CDOT reimbursement would be applied to other currently unfunded BRRTA
projects: widening from Desiree Drive east to Tari Drive, widening west of
I-25 to the west end of Baptist and a $13 million bridge over the railroad
tracks. (The extension and paving of Baptist Road east of the Roller Coaster
Road intersection to the Highway 83 and Hodgen Road intersection is not part
of BRRTA.)
In his conclusion, Glenn said,
-
"The interchange won’t be built unless we build it
ourselves."
-
"The next higher priority, the Highway 16 expansion,
was just funded, which is good for us."
-
"It’s a safety hazard now. It’s a transportation
nightmare. I was stuck on the (Baptist Road) off-ramp for seven minutes just
now."
-
The Board of Trustees are all volunteers and Monument
residents.
-
The tax benefits the town because all tax revenues go
directly to financing the interchange improvement.
Town Manager Green briefly reviewed a few highlights of the
PowerPoint slide presentation PBS&J project manager Steve Sandvik gave to
PPACG on Aug. 17, prior to their decision to upgrade the interchange to a
regional priority. The main purposes of the early financing are:
-
To expedite construction for public safety.
-
To relieve congestion and failing levels of service on
the Exit 158 interchange, Baptist Road, and Jackson Creek Parkway.
-
To save money by integrating simultaneous state
interchange and county road widening projects.
-
To take advantage of $1.286 million of commercial
right-of-way donated to BRRTA to expedite the tax initiative.
-
To avoid future unknown escalations of construction costs
in excess of inflation already experienced on current Baptist Road widening
project
Sandvik said that interchange construction, which would last
14-16 months per the essentially completed PBS&J design, could begin as soon
as:
-
The sales tax initiative is approved.
-
Rights-of-way transfer documentation is completed
-
Bids for construction are advertised and the winning bid
is awarded
Commissioner Williams gave his views on the state’s funding
priorities and why the temporary one-cent BRRTA sales tax ballot initiative
makes short-term reimbursement of BRRTA more likely, if approved in November:
-
After extensive research, there are only two options: a
taxpayer initiative for financing early construction to begin immediately
after a vote for the initiative or wait indefinitely for state funding,
perhaps 20 years or more.
-
BRRTA residents, primarily from Jackson Creek, will vote
on the initiative since they are most affected by the Baptist Road
interchange.
-
The majority of shoppers who will pay the majority of the
tax will come from outside of BRRTA, and pay directly for their use of
Baptist Road for access to stores within BRRTA – there are clearly not
enough shoppers in BRRTA to support a Wal-Mart, Kohl’s, Home Depot or the
other planned/projected regional stores.
-
The state has over a $10 billion backlog of unfunded
capital highway projects
-
The interchange improvement is already environmentally
cleared.
-
The interchange is part of a $525 million improvement
program, which includes a six-lane improvement for I-25 within El Paso
County, from the World Arena to County Line Road, with eight lanes from
North Academy Boulevard to Circle Drive.
-
Virtually everyone who will vote on the initiative has
moved here after the interchange was built, adding to its congestion.
-
The temporary BRRTA one-cent sales tax will bring the
rate up to competing stores in Colorado Springs and other parts of the
county, not make it higher, because Monument’s BOT chose not to be part of
PPRTA’s temporary one-cent sales tax.
-
Even in the highly unlikely event that CDOT does not pay
back BRRTA nor does the sales tax pay off the purely revenue bonds after 20
years, it would expire – the risk is entirely the bondholders’.
-
Immediate construction is cheaper, easier, and faster
after a favorable vote to privately finance the improvement, making Exit 158
functioning and safe as it was just a few years ago.
Commissioner Schooler also provided some of his views on the
ballot initiative:
-
The high PPACG priority that should have led to funding
this improvement five years ago was lost due to the economic downturn which
will now severely limit state capital highway funding indefinitely under
TABOR.
-
The only state funding that is guaranteed in the future
will be for maintenance and repairs of existing roads.
-
Excess revenues can only be allocated to capital
improvements, if they become available, under Colorado Senate Bill 1
-
PPACG has given the interchange a high enough regional
priority to make this category of funding very likely within the 2007-12
time frame of its current Transportation Improvement Program.
-
CDOT repaid private financing of the Powers and Platte
Boulevard interchange
-
His approved Aug. 17 motion to create an
intergovernmental agreement between CDOT and BRRTA for repayment of the
capital construction costs is based on this ballot initiative – the
agreement would be signed if the ballot initiative passes.
Some additional information was provided in statements made
by these officials in response to citizen questions:
-
The dangerous and troublesome light at the
Baptist-Struthers Road intersection will be eliminated when Struthers Road
is widened to four lanes and re-routed to the Baptist-Jackson Creek Parkway
intersection.
-
Construction by the county for its new Struthers Road
connection to Jackson Creek Parkway cannot begin until November due to
federal Preble’s mouse mitigation requirements.
-
The diamond configuration of the intersection will be
retained because a clover-leaf would be more than five times more expensive
due to the amount of commercial land and buildings that would have to be
paid for.
-
Traffic on the Baptist Road interchange at full Monument
region buildout will be less than the current amount of traffic for the
Woodmen Road I-25 interchange.
-
Both I-25 off ramps will have dual left-turn lanes.
-
The northbound I-25 off-ramp will have a "through
right-turn lane." Both I-25 on-ramps will also have a "through
right-turn lane" from Baptist Road.
-
There will be dual left-turn lanes in both directions
from the new eight-lane bridge over I-25 to the I-25 on-ramps
-
The Baptist-Struthers-Jackson Creek Parkway intersection
will have dual left-turn lanes in all four directions
-
There will be no extension of Mitchell Avenue across
extensive Preble’s mouse habitat to intersect Baptist Road unless the
mouse is de-listed by the Environmental Protection Agency and the state.
-
The northern edge of the eight-lane bridge must be eight
feet higher than the current bridge to provide sufficient clearance from the
planned I-25 grade, farther up Monument hill.
-
The westbound four-lane span will be built first while
traffic continues to use the existing two-lane bridge.
-
There will be "an interesting temporary detour
road" for the change in elevation when traffic is switched to the
northern span and the existing bridge is demolished to start construction on
the southern four-lane span.
-
The bridge will be wide enough for future widening of
I-25 to eight lanes on Monument Hill
The meeting adjourned at 7:55 p.m. The next BOT meeting is on
Tuesday, Sept. 5, due to the holiday weekend. Meetings are normally held at 6:30
p.m. on the first and third Monday of the month at Town Hall, 166 Second St.

Monument Planning Commission, August 9: Promontory
Pointe plans recommended for approval
By Jim Kendrick
The Monument Planning Commission unanimously approved the
Promontory Pointe plat and site plan proposals that had been continued from the
July 12 meeting because a consultant was late in sending notices to neighboring
property owners. Also approved were a major amendment to a Trails End
preliminary PD site plan and a proposed change to the town’s lighting
regulation. Commissioner John Kortgardner was absent.
Promontory Pointe preliminary/final plat approved
Director of Development Services Tom Kassawara noted that the
commissioners had already conducted a public hearing on the plat and site plan
July 12. He said there would also be public comment on both during this meeting
because of the previous notification problem.
Road name still not approved: The name of the extension
of Gleneagle Drive northward from Baptist Road through Promontory Pointe and
Home Place Ranch to Higby Road has still not been approved by the county. Landco
Properties, the developer of Promontory Pointe, did not want to use the name
Gleneagle Drive because it might imply that this development was part of
Gleneagle, a county development, even though concerns were expressed at hearings
that such name changes are confusing.
In 2005 Landco, HPR LLC (the developer of Home Place Ranch to
the north), and Classic Homes (the developer of Sanctuary Pointe to the east)
agreed to form three road improvement districts which would impose separate mill
levies to pay for the extension of Gleneagle Drive north to Higby Road, widening
of Higby Road from Home Place Ranch west to Jackson Creek Parkway, and widening
of Jackson Creek Boulevard to four lanes from the Monument Marketplace north to
Highway 105.
The name Ranch Point Road was selected to reflect the names
of all three contributing developments. However, the Enumerations Office of the
Pikes Peak Regional Building Department did not approve that name. The name
"Old Post," which had been assigned to a cul-de-sac within Promontory
Pointe, was then proposed for reassignment by town staff to the Gleneagle
extension. However, the proposed plat submitted at the July 12 hearing depicted
the name of the extension of Gleneagle Drive as Walkerton Drive, while the name
for this road shown on the site plan was Temperance Drive. The plat and site
plan submitted for the Aug. 9 hearing listed the name as Old Post Road. This
reassigned name and the new name for the affected cul-de-sac had not yet been
approved by the Enumerations Office.
This northward extension of Gleneagle Drive will be called
Ranch Point Road only within the Promontory Pointe and Home Place Ranch
annexations. The intersection of Higby and Ranch Point Roads will align with the
future southward extension of Furrow Road to Higby, in accordance with the
county’s Major Transportation Corridors Plan. Furrow Road, like Gleneagle
Drive, is in the county. Furrow Road, Ranch Point Road, and Gleneagle Drive will
form a single residential collector parallel to I-25 between County Line Road
and Northgate Road.
The county is widening and re-routing Struthers Road to
connect to Jackson Creek Parkway as part of the Baptist Road improvement—another
part of its Major Transportation Corridors Plan. This major frontage collector
parallel to I-25 will also connect Northgate Road and County Line Road.
Landco originally sought approval from Triview Metropolitan
District to avoid having to meet the county minor urban residential collector
standard called for in the county’s Major Transportation Corridors Plan, which
applies to Gleneagle Drive. The collector standard requires a 60-foot
right-of-way, no parking, and no driveways. Triview responded by creating a new
road category to meet Landco’s request for only a 50 foot right-of-way and
allowed on-street parking and driveways to each house.
On Nov. 9, 2005, citizens complained about safety and the
developer’s desire to maximize density at the Promontory Pointe PD sketch
plan. Several commissioners also specifically complained about the narrow
right-of-way and cars backing into traffic from driveway accesses for every lot
along this collector. The Planning Commission rejected the proposed PD sketch
plan. After a heavily attended four-hour hearing Feb. 6, Landco withdrew its
proposed sketch plan when the Board of Trustees appeared ready to vote against
it for the same reasons.
Town staff initiated a program to require unification of
Triview’s and the town’s development regulations. Eventually, Landco and
Triview dropped their insistence on creating a new road category and Landco
agreed to reconfigure the collector road to meet county standards. However,
neither of the plats submitted in July and August depicted the new frontage road
easements for driveways for the lots along Old Post Road to match those shown on
the site plans.
Kassawara reported that the final plat conformed to the
density of the PD sketch plan approved by the Board of Trustees on Jan. 3. The
final plat contains 284 single-family home lots on 77.80 acres. Road
rights-of-way total 24.41 acres. There are 14.64 acres of open space and park
tracts. Gross density is 2.43 dwelling units per acre. Net density is 3.08
dwelling units per acre. The developer will donate the cash equivalent of 4.5
acres of dedicated land to Lewis-Palmer School District 38.
The plat had been revised to address most of the technical
corrections requested by the staff in July, including a change of responsibility
for park maintenance from the town to Triview Metropolitan District. The
remaining minor technical corrections were addressed by a single condition that
says they "shall be made to the satisfaction of Town Staff prior to
recording" the plat.
Kassawara reported that referral comments from other agencies
had not yet been addressed. He recommended a condition that "All referral
comments shall be addressed to the satisfaction of Town Staff prior to
recording" the plat. He added that the plat was "pretty well buttoned
up and ready for a vote."
Principal Planner Karen Griffith said the proposed plat
conformed to the requirement for an equivalent land dedication for parks,
trails, and open space equal to at least 20 percent of the parcel and the design
principles outlined in the town’s subdivision regulations.
Public comment: Jackson Creek resident Steve Cummings
said that the increases in Promontory Pointe lot sizes along the western
boundary of the parcel were more generous next to Saber Creek Drive and Split
Creek Drive than Pistol Creek Drive and Misty Creek Drive. He asserted that the
southwestern Promontory Pointe lots were actually 4,000 square feet smaller than
adjacent Jackson Creek lots because the land in the trail easement at the rear
of these proposed lots cannot be used by the prospective landowners. He pointed
out that there were still no driveway easements depicted on the plat along the
main collector road.
Cummings also said that the Promontory Pointe drainage next
to his Misty Creek Drive lot was inadequate due to a lack of detention ponds and
that his lot had been damaged by stormwater runoff. He suggested moving a
proposed park closer to his lot to increase stormwater absorption.
Commissioner Tom Martin said that the lot size adjustments
along the south end of the western boundary were comparable to those to the
north and did not need to be further enlarged. He noted that the 30-foot
diameter treed islands added to the center of all cul-de-sacs were a significant
improvement. Kassawara concurred and said the town would make that a new design
standard for future development and noted that the remaining roadway in the
110-foot diameter cul-de-sacs had a large enough turning radius for fire
engines.
The other three conditions Kassawara recommended for the
proposed plat were:
-
Right-of-way for Baptist Road shall be dedicated to El
Paso County by Warranty Deed before recording the plat.
-
The name for the main north-south street that connects
with Gleneagle shall be approved by the town and El Paso County Enumerations
prior to recording.
-
The missing frontage road driveway easements on Old Post
Road must be added to the plat prior to recording.
The plat was unanimously approved with the five proposed
conditions.
Preliminary PD site plan approved
Kassawara said that all the town’s previous drainage,
detention pond, and lot size issues raised at previous hearings had been
resolved.
Public comment: Kingswood resident Gene Scalf said that
Landco had not given him a copy of the preliminary site plan as promised and he
had been unable to prepare comments. Kassawara said Scalf could review a copy of
the plan he was given and provide formal hearing comments at the Board of
Trustees hearing.
Kassawara then responded to the site plan comments Cummings
had presented earlier in the meeting. Kassawara said that he had reviewed and
approved their engineering plans for detention ponds and an outfall line that
connects to a Jackson Creek outfall line. Cummings replied that it was the open
space on the vacant Promontory Pointe land by his lot that was causing the
problem. Kassawara said there had been no grading on the Landco parcel other
than for Baptist Road widening. The flows Cummings was discussing were historic
natural flows that preceded construction of any houses in Jackson Creek.
Kassawara said that the 30-foot trail easements along the
western boundary of Promontory Pointe will be part of each of the privately
owned boundary lots and will be taxable in accordance with the PD sketch plan
approved by the Board of Trustees in January. These lots are approximately equal
in size to those along the eastern boundary of Jackson Creek. Kassawara also
noted that the 30-foot trail easement, as well as the fence that will be
installed on both sides of the trail will be maintained by Triview Metropolitan
District rather than the individual property owners. These improvements will be
built before building permits are issued for any of the affected houses.
Kassawara also said that the location of the parks had not
changed throughout the approval process due to the natural sloping topography of
the sites making them most appropriate for benches and picnic tables. "That’s
the place for the park due to the terrain."
The preliminary PD site plan was unanimously approved.
Trails End PD site plan major amendment approved
The Trails End land owner, Five Y Eyes Guys, LLC, sought
approval of a major amendment to the development’s design guidelines to more
than double the number of building elevations being offered by Richmond Homes as
well as increase the number of available colors, types of siding materials, and
decorative stone options. Kassawara said the recommended addition of larger
models and upgraded materials were consistent with the previously approved PD
guidelines. "More variety is a positive."
Public comment: A number of Santa Fe Trails residents
attended the meeting to register complaints about Trails End issues unrelated to
the proposed PD site plan amendment. However, Shoshone Trails homeowner Robert
Byers did say that he did not like the designs, colors, and materials used on
the few existing Trails End houses, because they did not match those of adjacent
Santa Fe Trails houses like his.
The other complaints came primarily from Trails End and Santa
Fe Trails residents who live along the boundary between the two developments and
were also unrelated to the hearing. They focused on the property owners’
inability to plant trees or build privacy fences due to a Monument Sanitation
District 20-foot major sewer collection line easement that extends 10 feet into
yards on either side of the subdivision boundary. Kassawara noted that fences
would prevent the district from having access to its line for cleaning and
repairs. He also noted that roots from shrubs and trees would puncture the
collection line, creating leaks that would cause cave-ins. Kassawara also noted
that a meeting would be held in these backyards the next morning, and he and
Monument Sanitation District Manager Mike Wicklund would answer questions from
homeowners.
Residents were unsatisfied with this statement. They said
Richmond Homes had failed to advise the purchasers of Trails End homes along the
northern boundary that they could not use the back of their yards due to the
sewer easement and the town was taxing them on property they could not use.
However, utility easements along the back 10-15 feet of residential properties
are very common in the Tri-Lakes region.
After the Aug. 10 meeting with property owners, Wicklund
recommended and the Monument Sanitation District board approved a policy at its
Aug. 15 meeting that allows homeowners to build fences along the rear boundary
of the affected perimeter lots as long as the owners acknowledge that they do so
at their own risk. The district reserves the right to take down the fences to
perform necessary sewer maintenance and repairs and will not be obligated to
replace them. Trees and shrubs will remain prohibited in the easement.
Several commissioners also asked Kassawara questions
unrelated to the design guidelines amendment hearing. Their questions focused
mostly on long-standing drainage problems in Santa Fe Trails. Kassawara said
these problems had been solved. The southwestern detention pond had been already
enlarged by the town at the developer’s expense and the outflow of the
northwestern detention pond had been redirected to the north to flow into Dirty
Woman Creek.
After further lengthy discussion about unrelated Santa Fe
Trails and Trails End issues, the commission approved the proposed additional
elevations, colors, and materials options.
Lighting regulation amendment approved
Griffith discussed her proposed amendment to provide a more
objective standard for lighting and minimize light pollution and glare from
future construction through the use of full cut-off or fully shielded fixtures.
She said it would apply primarily to commercial and multi-family building
proposals. The amendment is based on standards from the Illuminating Engineering
Society of North America that give lighting designers substantial flexibility.
The maximum illumination permitted is 0.1 foot-candles 20
feet outside the property line. Drawings called photometric grids that display
the distribution of varying illumination levels will be required submissions.
This maximum includes any interior illumination radiating outward through a
window. Exemptions are provided for temporary emergency, security, and holiday
lighting, as well as low-level illumination fixtures.
She noted that the Kings Soopers parking lot was one example
of construction that already complies with the proposed standard, providing
motorists with enough light for safety and security, yet having little if any
impact on neighboring properties.
Commissioner Carl Armijo asked if the consultant’s lighting
plans would require costly endorsement by a professional engineer. Kassawara
said only a letter from the lighting engineer stating that the proposed plan
complied with the amended code would be required.
The amendment was unanimously approved.
Kassawara asked for volunteers for a citizen committee to
write PD design standards for building elevations. Martin and Armijo
volunteered.
The meeting was adjourned at 8:55 p.m. The next meeting will
be at 6:30 p.m. Sept. 13, in Town Hall, 166 Second St. Meetings are normally
held on the second Wednesday of the month.

Baptist Road Rural Transportation
Authority, August 11: Draft language for sales tax discussed
By Jim Kendrick
The Baptist Road Rural Transportation Authority president,
County Commissioner Wayne Williams, announced that the state Transportation
Commission would be considering an intergovernmental agreement between Colorado
Department of Transportation (CDOT) and BRRTA on Aug. 17 regarding reimbursement
for revenue bond financing of Baptist Road interchange improvements. The board
also reviewed draft language for its November ballot initiative that proposes a
temporary one-cent sales tax within BRRTA to pay for revenue bonds to finance
early construction of the Baptist Road interchange.
County Commissioner Jim Bensberg and Monument Trustee Dave
Mertz were absent.
Frontage road update
Chaparral Hills resident Linda Silveira said she had been
working with El Paso County Department of Transportation project manager Andre
Brackin on plans for a privacy fence on the north side of her property. The
fence is to be built between her house and the frontage road on the south side
of Baptist Road that will provide alternative access to the Family of Christ
Church and the two lots to the east via Leather Chaps Drive. The driveway
accesses to Baptist Road for these three properties are being eliminated in
accordance with county standards for a major collector.
Silviera noted that Brackin was not in attendance and asked
the board to confirm that the fence would be built. Williams, confirmed that the
fence will be built.
Williams also noted that one of the two homes had been sold
to a church and said this showed that construction of the second church was
"illustrative of why we thought the frontage road was appropriate."
Silveira said, "I can think of worse neighbors." Williams added that
"It was kind of nice to drive by and see some of that (road) actually has
black top, curbs, and gutter."
Financial matters
The board unanimously approved payments for the district’s
audit and legal services. The board also approved payments of about $12 and $21
for property taxes for the rest of the year for two pieces of right-of-way. The
board’s attorney, Jim Hunsaker, noted it was cheaper to pay the minuscule tax
bills rather than continue trying to convince the state’s tax department
personnel that BRRTA was in fact tax-exempt. The board unanimously approved all
four payments.
Construction project updates
Monument Director of Development Services Tom Kassawara
reported that he had just received grading and utility relocation plans from
Mountain View Electric Association (MVEA) and the developer of the Monument
Ridge parcel. He said he would review them as soon as possible so that the
utility might begin to move the underground power lines that have slowed grading
and construction of the portion of Baptist Road opposite the King Soopers
shopping center. Monument Mayor Byron Glenn said that the on-site project
foreman had told him that "they were having a lot of problems with the
utility."
The cost of the MVEA relocation has more than doubled since
the contract was awarded for widening Baptist Road. MVEA has been slow in
relocating its lines along the entire length of the project and has been slow in
approving the regrading of the steep hill, construction of retention walls, and
relocation of its underground lines between the Monument Ridge development and
the Family of Christ Church. This has also caused delays by MVEA in approving
relocations of its lines in the Baptist Road right-of-way in front of the church
and the Monument Ridge development.
Planning development updates
Kassawara said that the Sanctuary Pointe preliminary
development proposal would be presented to the town’s Planning Commission in
September. No proposals had been submitted to his department for Home Place
Ranch. The Planning Commission had approved the preliminary/final plat and
preliminary PD site plan for Promontory Pointe (see article
on the Aug. 9 meeting for details) and they will be presented to the
Board of Trustees on Sept. 5.
Wording of ballot issue unresolved
There was a lengthy technical and philosophical discussion on
what would be the clearest way to word the proposal for a temporary one-cent
sales tax to finance revenue bonds to pay for construction of needed
improvements to the I-25 Baptist Road interchange before CDOT can pay for it in
2012 or later.
Hunsaker said the Taxpayer Bill of Rights amendment to the
state constitution requires that ballot questions be in a specific format, all
words have to be capitalized, and that the question be a single sentence. There
was consensus during the discussion that these requirements make it difficult to
draft wording that is not too long or convoluted for voters to quickly grasp and
understand. He noted Williams’ suggestion to use the Pikes Peak Rural
Transportation Authority ballot language as a guide to writing the draft the
board then discussed.
The board agreed on the following criteria for the temporary
tax initiative language:
-
The proposed temporary tax would be a standard Colorado
sales tax on anyone who shops within BRRTA, not a property tax on BRRTA
property owners.
-
The $25 million debt ceiling approved for BRRTA when it
was created in 1997 should be reduced to the smallest amount sufficient to
pay off all interchange debt should CDOT be unable to provide $15 million in
capital reimbursement to BRRTA.
-
The $125 million total debt repayment ceiling approved
for BRRTA when it was created should be reduced.
-
There is no existing BRRTA debt.
-
The ballot question must specify what the maximum
temporary sales tax revenue would be in the first year for payment on the
revenue bonds if the initiative is approved, and the amount must be large
enough to ensure that a refund is not required.
-
The term of the revenue bonds must be long enough so that
the bondholders are assured of an acceptable risk of return on their
investment.
-
The size of the bond issue must be large enough to pay
for all construction costs, bond issue administrative and overhead costs
including those for early payoff after CDOT reimbursement, all interest and
principal repayments if CDOT cannot pay back BRRTA, and a cash reserve to
cover the shortfall in initial temporary sales tax revenues during the first
few years after the bonds are issued until the rest of the planned stores
are built within BRRTA.
-
Any money received from CDOT that might be in excess of
the amount needed to liquidate the revenue bonds and pay off all other
construction costs would be applied to other BRRTA capital projects.
Williams emphasized that the wording of the ballot issue must
make the prospective taxpayers and holders of the revenue bonds comfortable. He
emphasized that nearly every registered voter within BRRTA moved here after the
authority was created. Hunsaker emphasized that the wording needed to be
complete enough to ensure that it was "bullet-proof" to any TABOR
challenge and eliminates any possibility of not authorizing enough capital
formation or tax revenue to pay for all aspects of construction and financing of
the project. Bond consultant Linda Clark, of Piper-Jaffrey, said that all these
parameters are a balancing act of estimates of future revenue and construction
costs while discussing options for the term of the bonds, size of the sales tax,
and the total amount of the bond issue.
After eliminating some parts of the draft language as
unnecessary, the board asked Hunsaker to redraft a shortened ballot question for
certification at a special meeting on Aug. 28. They asked him to reduce the debt
cap from $25 million to $21.5 million, reduce the maximum repayment cap from
$125 million to $50 million, and set the term of the bonds at 20 years. Schooler
said he felt confident that the state Transportation Board would approve the
repayment agreement on Aug. 17. Williams said the board could also approve that
agreement with CDOT for the future $15 million reimbursement on Aug. 28.
The meeting adjourned at 4:25 p.m.

Baptist Road Rural Transportation
Authority, August 28: Sales tax ballot question certified
By Jim Kendrick
The Baptist Road Rural Transportation Authority (BRRTA)
unanimously certified the language for the November ballot initiative and
unanimously approved an intergovernmental agreement for the Colorado Department
of Transportation (CDOT) to reimburse BRRTA for its proposed revenue bond
financing of Baptist Road interchange improvements. County Commissioner Jim
Bensberg was absent.
The board first held an executive session for about 20
minutes to hear legal advice from Authority Attorney Jim Hunsaker, of Grimshaw
and Harring, P.C., and County Attorney Bill Louis on questions related to the
ballot issue. No decisions or announcements were made afterward.
After a second lengthy public hearing for more citizen input,
the board further reduced the length of the ballot question and unanimously
certified the final draft text that proposes a temporary 1-cent sales tax within
BRRTA to pay for the interest and principal on revenue bonds to finance early
construction of I-25 Baptist Road interchange improvements.
(See article on the Aug. 11 BRRTA
meeting for discussion of the first public hearing on technical issues
regarding the text edits.)
Hunsaker said, "The certification was approved with the
understanding that a revised question might be required to be certified based
upon the advice of bond counsel. Nevertheless, the BRRTA Board expects the final
question to be substantially similar to the question certified today."
The certified text
"Shall Baptist Road Rural Transportation Authority (‘BRRTA’)
taxes be increased $1,500,000 in the first full fiscal year, and by whatever
amount of revenue is generated annually in every year of the tax thereafter, by
the imposition by BRRTA of a temporary sales and use tax pursuant to part 6,
article 4, title 43, of the Colorado Revised Statutes at the rate of 1.00% (one
cent per dollar) upon every transaction or other incident with respect to which
a sales and use tax is levied by the state of Colorado (excluding purchases of
food for domestic home consumption, prescription medications, residential
utility bills or other exempt transactions as detailed in articles 26 and 30,
title 39, as amended from time to time, of the Colorado Revised Statutes), such
taxes to be for the sole and exclusive purpose of funding the costs of
reconstruction of the Baptist Road interchange at I-25, which taxes shall be
subject to the following additional conditions:
-
This tax authorization is being approved in reliance
on the 1997 debt authorization;
-
The 1997 debt authorization is hereby reduced from
$25,000,000 in principal with a repayment of $125,000,000 to a new maximum
total of $21,500,000 in principal with a repayment cost not to exceed
$50,000,000;
-
Such taxes shall not commence unless and until the
previously authorized debt shall be issued, and shall terminate upon the
earlier of (1) such time as the debt and any refundings thereof are paid in
full or fully defeased, or (2) 20 years after commencement of such taxes;
-
The debt shall be paid from the proceeds of the taxes
authorized hereby and any reimbursements received by BRRTA from the Colorado
Department of Transportation?"
Mail-in ballot approved
The board also unanimously approved having a mail-in election
rather than a coordinated polling place election with the county.
County Commissioner Wayne Williams proposed the mail-in
election after noting that there are 12 November ballot initiatives. The board
unanimously approved Monument Town Clerk Scott Meszaros to be the designated
election official. He will be advised by Sue Blair, the special election expert
for R.S. Wells, the district’s management company, on the unique aspects of a
rural transportation authority mail-in election law.
Blair advised BRRTA to obtain a separate post office box at
the Monument Post Office (80132) for mailed ballots, since nearly everyone
living in BRRTA has a Monument postal address. The return address on the clearly
distinctive envelopes used to mail ballots to only registered voters will
indicate it is sent by BRRTA, with this dedicated Monument post office box
number and ZIP code to help ensure that it is not considered to be junk mail.
R.S. Wells will obtain the list of registered voters within BRRTA from the El
Paso County Clerk and Recorder and mail out the ballots for BRRTA.
Completed ballots must be mailed early enough to ensure that
they are received no later than 7 p.m. on Nov. 7, regardless of when they are
postmarked. If delivered after 7 p.m., they will not be counted. Ballots may
also be hand-delivered to Town Hall, 166 Second St.
Special Sept. 8 meeting scheduled
The board scheduled a special meeting for 2:30 p.m. on Sept.
8 in Town Hall for further certification of the final language if changes are
recommended by the bond attorney. The board will also give final approval of the
mail-in ballot procedures and policies.
Appointment of a county project manager requested
State Transportation Commission member Terry Schooler asked
that the board discuss appointing a county project manager on Sept. 8 for the
interchange project. The project manager would coordinate county Department of
Transportation pre-planning to be able to issue a request for bids within a few
days after the election if the voters approve the ballot initiative. Current
county policy is to not begin this kind of work until funding is appropriated
and allocated for a specific project. Williams and Hisey concurred and agreed to
ask the county Transportation Department to make an exception of this policy to
maximize savings and minimize the time it would take to complete both of the
integrated Baptist Road projects.

Palmer Lake Town Council Workshop, August
3: All agenda items continued due to applicants’ absences
By Jim Kendrick
None of the three applicants attended their land use
preliminary hearings at the Palmer Lake Town Council Workshop. Three members of
the council were also absent. There was no discussion of the three proposals,
though there was discussion for nearly an hour of several items not on the
agenda. Mayor Max Parker, Trustee Trudy Finan, and Trustee Gary Coleman were
absent. Trustee Richard Allen presided.
The only three items on the published agenda were hearings on
the following requests:
-
A sign permit request for Classic Catering by Anne Jones
and Company
-
A request for a change to the planned unit development
zone by Al Fritts for the Inn at Palmer Lake to divide the 27-acre parcel
into two roughly equal size lots
-
A request for a minor subdivision and conditional use by
Kreig Campbell for a proposed multi-use building on a lot behind the Speed
Trap Café building on Glenway that is currently zoned for single-family
residential.
"I can’t explain their (the applicants’)
absence." Allen said. "I do believe that at next week’s meeting we
certainly should take into consideration that they were not available for the
workshop and adjust accordingly." Trustee Susan Miner said the council
should learn why they were absent before passing judgment that might
"impact our course of action next week." Allen replied, "I didn’t
pass judgment, Susan. I said it should be taken into consideration." He
said that his remark was not a judgment nor would the applicants be penalized
for their absence, but a council decision could be delayed due to lack of
information presented at the workshop. All three proposals were continued
without discussion. They were all approved on Aug. 10. (See article
on the Aug. 10 meeting.)
Allen asked if the trustees had any other non-agenda items
they wanted to discuss.
Trustee Trish Flake suggested that a number of requirements
currently listed in the town code were not being complied with. She said that
minutes and bills are supposed to be read aloud at town council meetings, that
all trustee reports are to be written and read aloud, and that all minutes are
to be stored in a binder available for citizen review. She also noted that the
code authorizes a town manager position and the council should discuss
appointing a town engineer and improving fire coverage.
There was a lively discussion between staff members and Flake
about the actual need to read minutes and reports aloud to comply with a
19th-century ordinance regarding hand-written minutes and invoices in an age of
e-mail and laser printers. Town Clerk Della Gray said there is insufficient
shelf space on the administration building conference room literature racks for
binders currently on file for citizen review. She questioned the need to
generate even more binders of printed paper that would needlessly duplicate
official town records when few citizens or trustees ever ask to see any of the
numerous existing binders. Gray added that the staff has a policy to print and
give a copy of any town document or record to a citizen upon request and again
noted that there are very few of these requests.
Gray and Allen also noted that the town had tried having a
part-time town manager in the early 1990s and that the results were
unsatisfactory. There is little likelihood of Palmer Lake having revenue to pay
a full-time town manager based on several failed town tax initiatives and
subsequent councils have since rejected filling the position. Gray said that the
current form of government is formally recognized by the Colorado Municipal
League’s classification of "town council with no city manager" for
small Colorado towns that can’t afford to pay a town manager.
Allen suggested that other staff job descriptions should be
updated as well. He asked Flake and the other trustees and staff present to
submit lists of possible administrative updates to the town code for future
"meaningful discussion" by the council.
Allen announced that he would make a major policy statement
on fire inspections at the regular council meeting on Aug. 10 when the mayor was
present. He noted that six months had passed since the election, one-quarter of
the two-year election cycle, and said the council needed to be more pro-active
on completing initiatives, rather than only reacting to items placed on the
agenda by others.
Consultants help town promote itself: Miner reviewed a
recent meeting held by her Economic Development Committee with the state Office
of Economic Development and International Trade. She noted that several
officials and agencies throughout the county and region have offered to help her
committee develop a marketing strategy and program to better promote Palmer Lake
businesses and recreation. Miner said the committees and consultants are helping
the town decide what it wants to promote and develop in addition to its
"good old-fashioned, small-town American values." She also noted that
the highlight of the meeting was a slide show of Palmer Lake scenes prepared and
presented by local photographer Mark Kirkland and Stephanie Schmuckatelly of the
Tri-Lakes Center of the Arts.
Miner reported that most officials at the meeting were very
surprised to learn that Palmer Lake’s trustees, planning commissioners, and
committee members are unpaid. She also said that the consultants had found that
the town is "unwelcoming to visitors at all levels," is "only
being good at taking care of its own," and "has a reputation for being
anti-growth and anti-development." Miner said that reversing these negative
perceptions should be a priority.
Allen reported that the town’s consultant engineer, Paul
Gilbert, said earlier in the day that Tim Shanks’ controversial three-lot
development on the south fork of Shady Lane was in compliance with the existing
hillside ordinance that sharply restricts construction on steeply sloped town
lots. Allen also noted that no one was happy about the "contentious
issues" regarding erosion, mud, and stormwater runoff from Shanks’ lots
after repeated heavy summer rains. Allen said Shanks’ project was now moving
forward with corrections based on the input from staff, consultants, and
concerned citizens.
The meeting adjourned at 8 p.m.

Palmer Lake Town Council Meeting, August 10:
Fire Authority proposes new support agreement
By Jim Kendrick
Trustee Richard Allen announced that the Tri-Lakes Monument
Fire Authority (TLMFA) had proposed changes to the ambulance service agreement
between the Tri-Lakes Fire Protection District and the Palmer Lake Volunteer
Fire Department (PLVFD). Most of the PLVFD firefighters attended the meeting to
show their concern about the controversial proposal. The council also approved
three replat proposals. Trustee Trudy Finan was absent.
Committee reports
Mayor: Mayor Max Parker reported that he had attended the
forum sponsored by the Tri-Lakes Chamber of Commerce on July 21 and noted that
it should be a good forum in the future for the town’s economic development
proposals. He said he had also attended the Department of Local Affairs budget
workshop on July 27 with Trustee Jim Girlando and Town Clerk Della Gray. There
was a good discussion of Taxpayer Bill of Rights (TABOR) issues that will be
helpful for the development of the 2007 budget. He asked each department head to
have their portion of the 2007 budget drafted and submitted in time for the
September council meetings.
Hillside ordinance amendment discussed: Parker also
reported that he had discussed the application of the current hillside ordinance
to Tim Shanks’ three-lot Blue Dolphin development on the south fork of Shady
Lane with town consultant engineer Paul Gilbert and Town Attorney Larry Gaddis.
Parker said Gilbert had confirmed that Shanks’ construction had met the intent
of the hillside ordinance because excavation had been limited to less than 40
percent of the remainder of the parcel not set aside in a conservation easement.
Gaddis said that the hillside ordinance should be amended to
eliminate the existing loophole in state and town statutes that allows
excavation on the entire remainder of a hillside parcel (in excess of the town’s
40 percent limit) if a portion is first converted to a conservation easement.
His proposed amendment would exclude any conservation easements from the 40
percent calculation for the remainder of the parcel. Gaddis also emphasized that
Shanks had complied with the spirit and intent of the current town ordinance
after setting up a conservation easement even though he was not required to do
so under the existing state law and town code. Parker proposed a discussion of
the hillside ordinance amendment at the "town council
offsite/retreat," which was held Aug. 23.
There is currently a moratorium on further construction on
sloping lots affected by the current or amended hillside ordinance until Dec. 31
as a result of this controversy.
Alternative well water proposal for Palmer Lake: Parker
said he had made a preliminary inquiry about potential costs and legal issues
for using the town’s recently drilled D-3 well to help sustain the level of
water in Palmer Lake. This Denver aquifer well did not produce enough water—only
about 60 gallons per minute—to be useful for the town’s water system and has
been capped since it was tested for flow. Parker said he did not yet have firm
estimates for constructing a water line from the well to the lake and a separate
water line from the well to Monument Creek. The second line could provide
substitute augmentation water for any Monument Creek surface water that might be
diverted into the lake in addition to groundwater from the D-3 well. He said the
rough preliminary estimate for the project might be as high as $400,000. Parker
suggested that the council should also discuss at the retreat on Aug. 23 a
possible ballot initiative to fund this construction cost with a mill levy about
the same size as an expiring water system mill levy. A decision in favor of this
new proposed initiative would need to be made soon to meet the timetable for a
November ballot issue.
Allen asked if the Awake the Lake Committee had been part of
the process. Spokesman Jeff Hulsmann said he had just learned of this
alternative to the committee’s proposal to drill an agricultural well within
the lake to maintain its level. He added that either well would only be a near-
or mid-term solution for helping keep the lake full.
Roads: Roads Trustee Allen reported that the town
continues to use state and county road repair millings to fix the town’s dirt
roads that were washed out by summer storms. He noted that these millings were
used for repaving and dust control on Epworth Highway and other dirt roads to
the south.
Fire: Fire Trustee Gary Coleman discussed a proposed
change in the ambulance service agreement and reported the July fire department
statistics.
Coleman pointed out that most members of the volunteer fire
department were in attendance to show their concern about proposed changes in
the four-year-old ambulance service agreement between the Tri-Lakes Fire
Protection District (TLFPD) and PLVFD. He said the volunteer firefighters wanted
to learn about the new proposed agreement, which had not been provided to Chief
Phillip Beckman as required by the existing agreement. Coleman said Beckman and
Tri-Lakes Chief Robert Denboskie should meet first, per the existing agreement,
with Fire Trustee Coleman and then the council before Beckman discusses any
changes proposed by Tri-Lakes. Miner said that Tri-Lakes had tried to go around
the Palmer Lake fire chief and fire trustee in numerous past negotiations she
had participated in.
Allen said he had been given the proposed agreement and had
put it in Parker’s inbox. Allen, a Forest View Estates resident, is a neighbor
of Charlie Pocock, a long-time director and president of the TLFPD board and a
former Palmer Lake trustee.
The new draft agreement Tri-Lakes has proposed:
-
Changing the parties to the agreement from Tri-Lakes Fire
Protection District and Palmer Lake Volunteer Fire Department to Tri-Lakes
Monument Fire Authority and the Town of Palmer Lake.
-
Changing the scope of the agreement from ambulance and
medical services to emergency services by adding fire and hazardous material
emergency services.
-
Changing those responsible for representing Tri-Lakes and
PLVFD in discussions of day-to-day operational matters from the respective
fire chiefs to the Palmer Lake mayor and president of the TLMFA board.
-
Changing on-scene "incident command" from PLVFD
to Tri-Lakes at any Palmer Lake emergency scene and "TLMFA will retain
incident command until the incident commander deems it appropriate to
transfer command to PLVFD," reversing the current policy that "PLVFD
will retain scene control and turn patient control over to TLFPD for
transport of Advanced Life Support or Advanced Life Support
Procedures."
-
Eliminating the signature lines for Tri-Lakes and Palmer
Lake fire chiefs.
Background: The type of ambulance service provided to
Palmer Lake by Tri-Lakes Fire Protection District and efforts to unify PLVFD
with Tri-Lakes have been controversial for years. In November 2001, after eight
years of discussion, the Palmer Lake Town Council, Tri-Lakes Fire Protection
District, and Woodmoor/Monument Fire Protection District commissioned a
unification study by consultant Emergency Services Education and Consulting
Group (ESECG.) Mayor Nikki McDonald of Palmer Lake said at the time that she
was, "very hopeful the study will suggest feasible ways to improve service
for town residents." She also said she understood that any such arrangement
will require tax dollars from Palmer Lake residents and must, therefore, have
their approval. She also said she did not want the study to overlook the
valuable contribution of Palmer Lake’s corps of volunteers.
The purpose of the consultant’s study was to explore ways
to (1) avoid duplication and waste in area-wide equipment purchases and in
meeting construction funding, (2) improve emergency service training and
responsiveness throughout the area, and (3) examine service boundaries in light
of the location of existing fire stations, including those facilities outside
the service areas of study, to minimize the need for future capital expansion.
However, there were continuing areas of concern. Key members
of the North End Fire Chief’s Group had discontinued automatic aid to the
Tri-Lakes Fire Protection District in late September 2001 due to the Tri-Lakes
chief’s failure to participate in North End Group meetings and Tri-Lakes
firefighters’ failure to participate in joint North End Group training events.
"Automatic aid" means that whenever a call for service is made
anywhere in the North End Group area, all assigned districts are dispatched
automatically. Without an automatic aid agreement in place, other districts will
only respond to help an excluded district when directly asked for assistance.
With the consultant’s study funding agreement in place, the
Woodmoor/Monument District reinstated automatic mutual aid with Tri-Lakes. The
other adjacent North End Group districts—Donald Wescott Fire Protection
District in Gleneagle to the south, the Black Forest Fire and Rescue Protection
District to the east, and the Larkspur Fire and Rescue District to the north in
Douglas County did not reinstate automatic aid, however.
The Palmer Lake Town Council had also voted to cancel its
ambulance service agreement with the Tri-Lakes District on Nov. 8, 2001. It had
proposed a replacement contract with the Larkspur district. One reason given for
the change was that Tri-Lakes had not responded to every Palmer Lake call with a
paramedic on board the response vehicle. Larkspur had two crews complete with a
paramedic available around the clock at that time. According to Mayor McDonald,
Tri-Lakes was also undergoing substantial growth and the increased demand for
ambulance service within the Tri-Lakes District had increased the burden of
servicing Palmer Lake with paramedics.
The Tri-Lakes District vigorously disputed this assertion.
Tri-Lakes FPD Chief Keith Jensen attended the Dec. 13, 2001 Town Council meeting
and vowed that the Tri-Lakes district would ensure the availability of an ALS-qualified
paramedic on every call if that was what Palmer Lake required. After a heated
discussion, the Palmer Lake Town Council voted to defer contract termination
until representatives from the Tri-Lakes and Palmer Lake Boards could meet in
January to discuss the matter. Palmer Lake was represented at these meetings by
Fire Trustee Scott Russell, a PLVFD volunteer firefighter, and Trustee Susan
Miner.
During meetings in 2002, representatives of Palmer Lake and
Tri-Lakes attempted to iron out differences between the two jurisdictions that
were highlighted at the Dec. 13 council meeting. Miner said that the Palmer Lake
Town Council felt it was necessary and prudent for the safety of its residents
to insist on paramedic services on each emergency medical call.
A second source of unification controversy has been the lack
of a town mill levy for emergency fire and ambulance services. The Town Council
approved a 6.0 mill ballot initiative for the April 2002 election. The Tri-Lakes
property tax levy is 7.0 mills. Woodmoor/Monument’s mill levy is 9.4 mills.
The ballot initiative would have raised about $118,000 in lieu of the
long-standing annual $40,000 budget line item. This latter amount is not enough
to cover all PLVFD expenses, requiring several fundraising events by the PLVFD
Association each year to meet the annual lease-purchase payment for the
department’s fire engine. Unification would have required that all three
entities have a property tax of about the same size, and this ballot initiative
was advertised as the town’s first step toward unification. The citizens of
Palmer Lake defeated that 2002 property tax ballot initiative (105-154).
A third source of controversy in 2003 was Tri-Lakes’
insistence on building a new staffed station on the property it already owned
for its unstaffed station at Roller Coaster Road and Highway 105 rather than at
the Highway 83 location recommended by the consultant’s study. Tri-Lakes
reportedly threatened to terminate ambulance service when the Palmer Lake Town
Council opposed Tri-Lakes’ request for a county zoning variance for the Roller
Coaster station at Board of County Commissioners hearings in May and June. The
Donald Wescott Fire Protection District Board also opposed the Roller Coaster
station zoning variance at those meetings.
Initially the county commissioners did not approve the
Tri-Lakes request because of the ambulance service and consultant’s study
controversies. There were also protests from neighbors of the existing unstaffed
station regarding a continuously staffed fire station in an area zoned
single-family residential. The commissioners later approved the variance in
December after Tri-Lakes publicly promised not to discontinue ambulance service
to Palmer Lake and many of the neighbors changed their positions on the proposed
fully staffed station. PLVFD and DWFPD remained opposed to the variance at the
December meeting.
After the town and the two districts approved a joint
resolution in October 2002, to move forward with unification, negotiations
between the three entities broke down completely by early 2004.
A separate unification agreement was signed between Woodmoor/Monument
and Donald Wescott Fire Protection District boards in early 2004. This new
agreement also offered membership to Tri-Lakes, but they declined to
participate. However, this second agreement was effectively dissolved within
months after a significant change in the membership of the Woodmoor/Monument
board following the May 2004 special district election.
Since then, Tri-Lakes and Woodmoor-Monument formed a fire
authority without offering participation to Palmer Lake or Wescott. The
Tri-Lakes Monument Fire Authority was created in January 2005. Woodmoor/Monument
unilaterally rescinded its unification agreement with Wescott. Neither PLVFD nor
Wescott has expressed interest in joining TLMFA since it was created.
The fire authority combines Tri-Lakes’ and Woodmoor/Monument’s
operational resources. The Woodmoor/Monument incident command Blazers have been
moved to Tri-Lakes Station One and the Woodmoor/Monument ladder truck is
frequently re-deployed to this Tri-Lakes station as well, due to the Tri-Lakes
ladder truck being frequently out of service.
However, each fire district remains a separate entity with
its own board for the purpose of raising revenue, conducting budgeting and
auditing functions, maintaining its own infrastructure, and providing
operational funding to the authority. The constituents of the Woodmoor/Monument
district continue to pay a 34 percent higher property tax mill levy than
Tri-Lakes even though each district now receives essentially the same level of
service.
Palmer Lake narrowly rejected a ballot initiative proposing a
half-cent sales tax (rather than a property tax) to fund PLVFD in April by just
six votes. The same ballot issue for a half-cent sales tax for the fire
department will be on the ballot again in November. The town budget still
provides about $40,000 annually to PLVFD and Association fundraisers continue as
well.
Tri-Lakes ambulance service contract still controversial: At
the Aug. 10 town council meeting, there was a lengthy discussion between Allen
and Miner about the history of ambulance and unification negotiations with
Tri-Lakes. Allen said Miner was biased against Tri-Lakes. Miner said Allen and
the new trustees needed to learn the complicated history to understand why
unification negotiations had always been unsuccessful. Some trustees said that
the council should consider the new proposal objectively despite this history.
Miner and Coleman noted that Tri-Lakes was still not
following the written procedures for negotiations because it had used Allen to
present its case to Parker instead of Chief Beckman. Allen said he had merely
delivered the document to the town administration building as a courtesy to
Tri-Lakes Battalion Chief Bryan Jack. Miner said Jack knew that he should have
personally given the document directly to Beckman.
Gaddis concurred with Miner and said the board has always
believed that negotiations should start at the chief-to-chief level. Gaddis
added that PLVFD recommendations are brought to the fire trustee, who then
presents them to the council. Assistant PLVFD Fire Chief Robert Lee, speaking
for the firefighters in attendance, said that they had still not seen the
proposed agreement and that it looked like the Tri-Lakes board was "going
behind their backs again."
Discussion ended at that moment, due to all the firefighters’
beepers going off. They left immediately to respond to an emergency dispatch.
Copies of the existing and proposed service agreements were subsequently passed
out to the trustees for their review prior to a discussion on negotiations with
Tri-Lakes at the offsite/retreat meeting on Aug. 23.
Coleman reported that the Palmer Lake Volunteer Fire
Department had 28 calls in July, of which 12 were for mutual aid. There were
nine medical calls, three fire calls, eight wildland fire calls, and one traffic
accident plus two public assists and five other calls. He said the volunteers
had also supported a Palmer Lake Library open house on July 27 and the historic
Estemere mansion open house on July 29 with engine displays. He added that the
department had received a Wildland Fire Grant for new pants and shirts from the
Colorado Wildland Service.
There were 165 calls for police service in July, down from
172 last July, with nine custody arrests and 62 traffic citations reported.
PLVFD roof repair authorized: The council unanimously
authorized Buildings Trustee Trish Flake to select one of three bids to repair
the leaking roof of the PLVFD fire station and initiate needed construction
prior to the next council meeting in September. The bids ranged from $13,800 to
$16,600. Contract selection was deferred because none of the bids included the
small additional cost for replacing wood supports under the roof that had been
found to be damaged after the bid request was published.
Flake also reported that the town would seek a different kind
of Colorado Tennis Association (CTA) grant to resurface the town’s tennis
courts rather than try to arrange for five years of CTA-approved tennis lessons
which was a condition of the previously awarded grant. After writing the winning
grant proposal, Palmer Lake tennis instructor Kim Makower withdrew his offer of
five years of instructional services in May following a dispute with the council
over the scheduling of a formal public relations grant presentation ceremony at
a scheduled town council meeting, another condition of the original grant, and
Makower’s unsuccessful run for mayor.
Economic Development: Economic Development Trustee Miner
reported that her committee was forming citizen teams to perform the community
assessments for the town’s economic planning consultants. She also reviewed
the progress report she gave the previous week at the workshop meeting. (See article
on the Aug. 3 meeting.)
Awake the Lake: Awake the Lake spokesman Jeff Hulsmann
expressed concern and surprise that Parker was researching plans to use the town’s
D-3 well to maintain the level of Palmer Lake instead of his committee’s
proposal to dig a new well in the lake. He said the sudden change in direction
might discourage support members of the county Parks Department and other state
and county agencies who are looking for an integrated long-term lake development
plan before giving the town supporting grants.
Fire hydrant issue discussed and dismissed: Allen said
that the town had not supported hydrant testing in Forest View Estates on July
10 during an Insurance Services Organization (ISO) inspection of Tri-Lakes Fire
Protection District. Allen is a Forest View Estates resident. This subdivision
elected to continue to be taxed as part of the Tri-Lakes special district after
it sought annexation by the Town of Palmer Lake, even though PLVFD would provide
service to the area with no dedicated property tax. Allen expressed concern that
Mayor Parker’s decision not to allow town hydrants to be tested by ISO for
maximum flow would cause insurance rates to go up in Forest View Estates.
Parker responded by saying that town Water Supervisor Steve
Orcutt had recommended against testing on that specific day because Orcutt was
scheduled to be out of town. Orcutt was not notified by Tri-Lakes Battalion
Chief Jack of the ISO testing until 4:30 p.m. the previous day. Parker said
Orcutt advised him that hydrant operation by personnel other than town water
employees might impose too high a risk on aging downtown residential water
mains. Orcutt was also concerned that all 12 Forest View Estates hydrants might
be opened to maximum flow at the same time, creating a muddy water problem
similar to that caused in late June 2005 when dechlorinated drinking water was
being used to fill Palmer Lake and caused the town’s groundwater pump to fail.
There was a lengthy discussion about whether the town should
take advantage of what Allen called "free testing." Some citizens did
not understand the ISO inspection process and expressed concerns about whether
the hydrants in town were functional. However, town hydrants are routinely
tested about twice a year, as they are in other regional water and fire
districts, while ISO tests hydrants only every 15 years. Miner said too much
weight was being given by Allen and troubled citizens to a test that occurs so
infrequently. Every town hydrant was opened and tested after the town’s well
pump failed while filling Palmer Lake last summer.
Insurance rates for Forest View Estates are determined by the
town’s ISO ratings, not those of Tri-Lakes. Palmer Lake will have its 15-year
ISO inspection two years from now. On Aug. 11, the day after this meeting, ISO
agreed to an alternative method, eliminating the issue.
Land use requests approved: The council approved three
land use applications for the following:
-
A sign permit request for Classic Catering by Anne Jones
and Company.
-
A request for a change to planned urban development zone
by Al Fritts for the Inn at Palmer Lake to divide the 27-acre parcel into
two roughly equal size lots.
-
A request for a minor subdivision and conditional use by
Kreig Campbell for a proposed multi-use building on a lot behind the Speed
Trap Café building on the southeast corner of Glenway and Valley Crescent
that is currently zoned for single-family residential.
Jones’ request was approved unanimously with no discussion.
Campbell noted that he had made the changes to his multi-use
commercial and residential building that had been requested by the trustees.
Coleman, who prepared Campbell’s subdivision drawings, recused himself from
the vote on Campbell’s proposal after Town Attorney Gaddis said he should. The
other council members approved the request unanimously. The proposal however,
will also require a hearing and approval by the town’s Board of Adjustments
for variances on setbacks and the reduced number of on-site parking places in
the proposed design.
Gaddis recommended that the council approve Fritts’s final
drawings on the condition that Gaddis would review and approve all the notes on
easements and detention ponds within a day or two before Fritts had the final
Mylar copy prepared for recording the replat documentation with the county.
Coleman opposed the subdivision request again for a wide
variety of reasons, as he had at every council and Planning Commission hearing
he attended this year. Coleman lives in the Rancho Iracema development next to
the Training Mission International and the Inn at Palmer Divide buildings, both
of which Fritts developed. Coleman’s driveway runs through an easement on the
Training Mission International property. Coleman did not recuse himself on any
of the council votes regarding Fritts’s request since hearings began in
January. Fritts asked to subdivide his lot into two parts at the request of the
Small Business Administration and Fritts’s long-term mortgage bank.
Fritts once again said there was no legal basis for any of
Coleman’s numerous objections and requests for further review and approval by
outside agencies. Gaddis confirmed that Fritts was correct. The council approved
the replat (5-1) with Coleman opposed. When Coleman tried to express further
objections after the vote, Parker said, "That’s enough."
Water membership contracts approved: The council approved
annual contract renewals for continuing town membership in the El Paso County
Water Authority and the Palmer Divide Water Group, totaling $6,000. Palmer Lake’s
dues are a tiny fraction of the total annual operating budget for both
organizations, which represent towns and water districts at water meetings at
the federal/state and county levels respectively.
Hulsmann said he opposed the contract renewals because he had
never heard of either organization. Gaddis disagreed and said the town could not
afford to "be left out of discussions because water’s too
important." He also noted that both groups were large enough that water
officials needed to listen to them. Flake said she agreed with Hulsmann and
voted against the renewals, producing a (5-1) vote on each.
Public comment
Resident Jennifer Farmer said that Palmer Lake needed a town
manager. Hulsmann also asked the council to reconsider its position on filling
the volunteer town manager position, noting that there are many retired military
officers and executives in the area.
Gaddis said he had drafted the original ordinance in 1988
that authorized a town manager position, but that results with volunteer
managers had been uniformly counterproductive. He also noted that in most other
Colorado towns that are the same size as Palmer Lake, the town managers turn
over every 18 months and make lots of mistakes because they never really learn
how to do the job.
Resident Denise Kokes said she had received a slow response
(15 minutes) from the Palmer Lake Police Department when she reported a
disturbance at the Palmer Lake Elementary School’s new playground. When
questioned by Parker and Gray about the circumstances of her call, Kokes could
not remember which police organization she had called or how her call was
transferred to the Sheriff’s dispatch center. Gray pointed out that Palmer
Lake police take their own phone calls and these phone calls are not transferred
to the Sheriff’s Office. There are inherent delays when the county dispatchers
have to ask a lengthy series of questions to determine where the caller lives
and which agency should receive the call.
The meeting adjourned at 10 p.m. The next workshop meeting is
at 7 p.m. on Sept. 7 in Town Hall, 28 Valley Crescent. The next regular council
meeting is at 7 p.m. on Sept. 14 in Town Hall. The workshops are normally held
the first Thursday of the month. The regular meetings are normally held the
second Thursday of the month.

Palmer Lake Planning Commission, August 16: Three
proposals recommended for approval
By Jim Kendrick
The Palmer Lake Planning Commission unanimously approved two
requests for vacation and replat and one change in a planned unit development
for a single family residence. Chairman John Cressman and Commissioner Sharon
Solheim were absent. Vice Chairman Ken Trombley presided.
George Parsons’ request for vacation and replat of adjacent
lots at 164 and 172 Shady Lane (Lots 23 and 24) was unanimously approved without
public or commissioner comment. Parsons owns both lots and each has a house on
it. His home and garage are on Lot 23 (164 Shady Lane), which is 5,500 square
feet. The structures span the lot line between these two lots and extend onto
Lot 24 to the east, which is 10,935 square feet. The other house Parsons owns is
on the east side of Lot 24, well away from the common boundary between these
lots. Parsons’ request moves the lot line to about halfway between the two
buildings. The proposed lot at 164 Shady Lane increases to 11,000 square feet
and the other lot decreases to 5,435 square feet. All setback requirements would
be met for both houses by this proposal. Parsons had previous approval for the
vacation of the portion of an unused 20-foot town right-of-way that is
overlapped by the east edge of Lot 24. His recorded plat should show the
Ordinance number and the County’s Reception number proving when the
right-of-way was vacated.
Thomas Patrick, with the support of the Pinecrest Homeowner’s
Association, requested permission to build a single-family home and garage on
vacant Lot 8 at the west end of Pinecrest Way. This 33,904-square-foot flag lot
has a very large area suitable for building a home and garage though a portion
is steeply sloped. There are no issues regarding compliance with the town’s
current or expected future hillside ordinance. Patrick’s request was
unanimously approved.
Susan O’Banion requested a vacation and replat of her
property at 455 Clio Ave. Her proposal would divide the existing two lots into
three lots. The existing single-family home to the west, at Clio and Virginia
Avenue, would be on the new Lot 1. The existing garage in the center of O’Banion’s
property would be on the new Lot 2, and the vacant land to the east would become
Lot 3. O’Banion reported that she plans to obtain water and sewer taps and
convert the garage to a house.
Vice Chairman Trombley reminded O’Banion of the commission’s
notice to her at the Aug. 9 workshop meeting that she would have to get Board of
Adjustment approval of variances for the current house and garage that were in
violation of the zoned setbacks when she bought the property, if she ever wanted
to sell either of them. He also noted that making the new vacant Lot 3 so small,
it would be hard to meet current setback requirements if she or a buyer tried to
construct a building and that she would be creating her own hardship. O’Banion
agreed with Trombley and said she had no plans to sell any of the three proposed
properties and had no plans to build on the proposed vacant Lot 3. O’Banion’s
request was unanimously approved.
The meeting adjourned at 7:14 p.m. The next Planning
Commission workshop meeting is at 7 p.m. Aug 13 in Town Hall, 28 Valley
Crescent. The next regular meeting is at 7 p.m. Aug 20 in Town Hall.

Donala Water and Sanitation District, August
21: Area water groups work to find supplemental water sources
By Sue Wielgopolan
The El Paso County Water Authority and the Palmer Divide
Water Group have been working to identify additional available surface water
sources and establish relationships with potential providers. Donala manager
Dana Duthie updated the board on the latest developments. The Palmer Divide
Water Group in particular discussed three options for additional water,
including agricultural agreements, a satellite well field in the Greenland Ranch
area, and possible recharge storage in the Black Squirrel aquifer.
The district’s annual audit revealed no irregularities,
although the firm performing the audit made minor accounting recommendations. A
portion of the district’s waste plant expansion loan may come from federal
grant funds. If so, it will have to provide a separate report documenting how
those funds are spent.
Donala waits for release of approved loan funds
Duthie told the board that the Colorado Department of Public
Health and the Environment temporarily blocked the release of loan funds for the
expansion of the Upper Monument Creek Regional Wastewater Treatment Facility.
Last fall, the Health Department and the Colorado Water and Power Authority
approved loans for $5 million each to Triview Metro District and Donala for the
expansion.
But the state Health Department recently refused to authorize
the issuance of checks to cover bills for the plant expansion until a formal
public hearing on the proposed changes to the facility had been held. The
hearing is required as part of producing the environmental impact statement.
The three partners in the plant—Donala, Triview, and Forest
Lakes Metro District—scheduled a public hearing for July 28, but no one from
the public attended. Duthie submitted documentation of the hearing to the state
Health Department, but has not yet received a response.
Duthie told the board that two bills from general contractor
Weaver Construction and several invoices for plant design engineering remain
unpaid.
Additional service line for underpowered waste plant delayed
Duthie told board members that electrical engineer Mark
Reisinger designed a setup to provide temporary power to the equalization basin
until Mountain View Electric Association (MVEA) is able to furnish a permanent
source. The Upper Monument Creek Facility may have to wait for up to 36 weeks
for an additional permanent power line, said Duthie. According to MVEA, extended
delivery time for the necessary transformer is the problem.
Although the existing service was adequate to power the old
plant, it is insufficient to run the many pumps and blowers that are part of the
expansion.
Duthie showed photos of the construction site and talked
about project progress. He said that the contractor was doing the final pour on
the equalization basin walls, and would then start on construction of the
catwalk. The screen room and influent station walls were scheduled to go up the
following week
Until the additional permanent power line has been installed,
temporary power lines will provide service to eight mixers in the equalization
basin. Duthie told the board maximum flow periods are already pushing plant
capacity; the basin is needed to store sewage for processing during off-peak
hours.
The diesel-powered backup generator currently used by the
Upper Monument Creek facility has been determined to be inadequate to handle the
greater power requirements of the expanded plant. If the generator was used only
during power outages, it might be sufficient. However, it is also used to run
the plant when the facility is taken offline during peak electrical demand hours
as part of a power partner program with MVEA. Mountain View rewards large power
users with significant cost savings in the form of credits when the users agree
to go offline during peak use hours, which reduces the total demand on the power
grid.
Two more generators will be needed at a cost to the district
of $360,000 for both. The units will take approximately 20 weeks to deliver.
El Paso County Water Authority activities
Duthie, who is also treasurer of the El Paso County Water
Authority (EPCWA), briefed the board on the major topics addressed during the
authority’s most recent meeting. Information is available on the authority’s
new website at www.epcwa.com.
Transit loss model funding: The transit loss study and
model has reached a point where participants must decide on a plan for funding
the operation of the model. The U.S. Geological Survey will perform the work
under contract, which will include maintaining the gauging stations and computer
model.
The water authority is hesitant to assume responsibility for
administration of the costs, which would represent a significant accounting
function.
Executive agent Gary Barber has been suggested as a likely
candidate to act as administrator, as long as his salary is proportionately
increased. Eventually, model participants may decide to hire part-time help to
take over those duties.
As yet, the agencies contributing to the study and model have
not reached consensus on how each entity’s share of the costs will be decided.
The issue of allowing non-governmental participants has also not been adequately
addressed. The Fountain Mutual Ditch Co. wants to be included but will need to
reimburse the other entities an undetermined proportionate share for the initial
study.
Black Squirrel aquifer recharge to be studied: The
Colorado Water Conservation Board may co-sponsor a study of the Black Squirrel
Basin as a possible recharge/storage site, along with other local entities
including Cherokee Metropolitan District, the Upper Black Squirrel Groundwater
Management District, the Sunset Metropolitan District, and Colorado Springs. The
study would assess feasibility and determine wells and infrastructure needed.
Cost and water quality are also considerations.
Duthie noted that recharge water would have to be treated to
a high level of purity to avoid contamination of the entire alluvial aquifer.
The Cherokee Water District previously conducted a pilot
study on using the shallow closed basin for storage. Effluent was spread on 20
acres, allowed to percolate through the soil, and pumped out again from Black
Squirrel Creek, so some preliminary information is already available.
The Black Squirrel Basin is attractive to northern El Paso
County water suppliers because of its proximity to the area and its status as a
closed basin, meaning it is not connected to the Arkansas.
Duthie told the board that the water authority may buy into
the study if the basin appears to be the only real option for large-capacity
water storage.
Palmer Divide Water Group meetings
Colorado Springs Utilities addresses pipeline request again:
Duthie reported that on July 19 two Colorado Springs Utilities (CSU) staff
members met for the second time with the Palmer Divide Water Group to discuss
Tri-Lakes-area water providers’ repeated requests for inclusion as partners in
the city’s Southern Delivery System (SDS) pipeline. CSU water supply manager
Wayne Vanderschuere hinted again at possible future cooperation but would offer
no assurances of participation in the SDS or any other CSU project.
Courtney Brand, project engineer and geologist for CSU, also
attended the meeting.
Vanderschuere urged that northern El Paso County water
providers be patient and reiterated that the SDS is too far along in the process
to start over or to incorporate major revisions. Duthie said he believes any
changes to the SDS after one of the environmental impact statement alternatives
has been accepted would require an additional environmental assessment at the
very least.
The Palmer Divide Water Group (PDWG) has been researching
options for alleviating the inevitable future water supply shortage facing
communities in the Tri-Lakes area as the aquifers are depleted. Only a renewable
source will solve the problem.
The PDWG would like to be able to set up agreements with
Arkansas Valley farmers to fallow a percentage of their land each year and sell
the water to northern El Paso County providers. To that end, the PDWG has
established relationships with potential Arkansas water providers Pure Cycle
Corp., the Southeast Water Conservancy District, the Lower Arkansas Water
Conservancy District, and the City of Aurora. The PDWG has also approached Mark
Morley, co-owner of Brush Hollow Reservoir, indicating interest in using the
lake as a storage facility. But the group needs a transport system to bring the
water north, hence its interest in partnering with Colorado Springs on the SDS.
Vanderschuere told the group that CSU has also been working
on setting up rotating/fallowing agreements with Valley farmers, and intimated
that partnerships may be available after the city has contracts in hand if
Tri-Lakes-area providers don’t interfere with the SDS process.
Other obstacles must still be overcome before Colorado
Springs will consider entering into any partnership with northern county
providers. Mayor Lionel Rivera has stated that cooperation on stormwater issues
is a prerequisite, and the City Council disapproves of what it sees as explosive
growth in communities outside city limits.
Duthie voiced his opinion to Donala members that the City
Council should view rapid growth as a regional problem that all entities,
including Colorado Springs, should address. He also pointed out that CSU is
struggling with stormwater mitigation and is having problems selling its own
program to residents.
Satellite well field may be good short-term option for PDWG
members: The PDWG discussed establishing a satellite well field north of the
Palmer Divide. The Colorado Water Conservation Board is offering a 4 percent
loanfor qualifying water projects. Engineers are evaluating several candidate
ranches in the Greenland Ranch area.
Wells in the Tri-Lakes region are exhibiting a significant
interference effect; overlap of the wells’ "cones of influence"
seems to be reducing yield. Area water providers hope that locating additional
wells far from existing ones may extend the life of the wells and the aquifers.
PDWG considers establishment of area-wide conservation plan:
Palmer Divide members also discussed creating an area-wide conservation plan.
Because Tri-Lakes providers are drawing from the same aquifers, all must
participate in order for the programs to be effective. In addition, districts
exceeding use of 2,000 acre-feet per year or receiving state grants are required
by the state to have a written conservation plan. Though Tri-Lakes-area
providers do not presently fall into either of those categories, the group wants
to be proactive, especially since applying for Colorado Water Conservation Board
loans may invoke the plan requirement.
Duthie told the board that Donala already has water
conservation measures in place, though they are not formally documented. The
district has a graduated rate structure that charges higher rates for higher
use. Donala encourages xeriscaping and maximizes utilization of reuse water and
effluent.
Most conservation plans include some form of watering
restrictions. PDWG members like the Woodmoor district’s demand management
program, which essentially asks residents to limit sprinkler system watering to
every third day between 6 p.m. and 10 a.m. Participation is voluntary. Similar
programs have been favorably received in other Front Range communities.
Bamberger economic study completed: A study commissioned
by the PDWG and authored by Bamberger Group documenting the benefits of
Tri-Lakes communities to the Colorado Springs economy is complete. As expected,
the economic consulting firm found that northern county areas contributed
significantly more to the city’s economy than it costs in lost tax revenues
and service increases.
PDWG members were given an opportunity to provide feedback to
the study. Now it must decide as a group how to present the conclusions to the
city of Colorado Springs. The Colorado Springs City Council has long held the
opinion that growth outside the city’s boundaries drains tax revenue and is of
negligible benefit overall, and has used that reasoning to discourage any
regional cooperation that could benefit growth, especially in regards to water
resources.
The group has yet to decide how to use the study’s results
to its best advantage.
CSU’s Northgate lift station moves forward
Disregarding the recommendation of its advisory water quality
council, the Pikes Peak Area Council of Governments (PPACG) recommended that CSU’s
proposed new lift station off Northgate Road be approved. The Pikes Peak Area
Water Quality Committee, of which Duthie is a member, had previously recommended
disapproval based on the fact that the lift station was redundant. Donala’s
lift station just 400 feet away has the capacity to handle the 49 homes Picolan
plans to build off Doral Way. The water quality committee encourages
consolidation of facilities whenever feasible.
The PPACG decided to recommend approval based on a tentative
agreement with Donala to provide a line to CSU’s station for emergency backup
should the city’s lift station fail. The new station will cost CSU
approximately $400,000 to build.
Mining museum seeks inclusion
Although Mining Museum curators have never spoken directly
with Donala staff, Duthie said that attorney Sandy McDougal had recently
informed the district that the museum was interested in inclusion.
Duthie suggested that since all of the buildings on the
property were probably not plumbed for water and sewer, board members might
consider charging tap fees for only two buildings. He added that if the museum
generated a significant amount of grease from eating facilities, a grease trap
would be needed to properly dispose of the waste.
According to Duthie, attorney Julianne Woldridge was putting
together a petition for inclusion.
Well 2A down, waiting for permit to redrill
Duthie told board members that redrilling of Well 2A has been
moved up, as the Arapahoe well is inoperable anyway because the pump motor
"is fried." Donala had planned to lower the pump in 2A to increase
yield. However, because the casing in the active well interior is offset,
technicians are unable to lower the pump any farther.
To reach a lower depth, Donala must drill a new well nearby
and plug the old cavity with cement. The district has applied to the state
engineer’s office for the required permit, but has not yet received it.
New Donala well will be located in Fox Run Park
Donala plans to drill a new Arapahoe aquifer well inside Fox
Run Park south of the playing fields and west of the Stella Drive entrance.
Duthie said the El Paso County Commissioners must still approve the well permit,
which he hopes to attain this fall. GMS engineering is preparing a legal
description of the site.
The district’s agreement with El Paso County Regional Parks
includes a free 6-inch tap for the park in exchange for the well easement.
Donala will also install a metering vault to monitor future use of Donala well
water by the park.
Duthie said that the park fills its two ponds from its own
Denver aquifer wells. At present, the wells run 24 hours a day and show no sign
of slowing. If and when those wells are no longer adequate to sustain the level
in the ponds and provide water for the restrooms, the park can switch over to
using its Donala tap.
Pipeline looping Triview, Donala water systems being installed
Rocky Mountain Materials and Asphalt is installing the
$132,000 pipeline linking Triview Metro District’s water system with Donala’s.
Rocky Mountain Asphalt is the contractor hired by the county to expand Baptist
Road.
The Donala board of directors passed a resolution and sent an
intergovernmental agreement for the Triview board to sign earlier this summer
that committed the two districts to splitting the cost of the pipeline. As yet,
Donala has not received a response from Triview.
Duthie wanted to get the pipeline installed while Baptist was
torn up, reasoning that the cost would be significantly less than if the
neighboring entities had to tear up completed road surface to put in the
connecting line. He decided to finance Triview’s portion if necessary, and
charge interest should the metro district fail to come up with its share in a
timely fashion.
Duthie is waiting to discuss the matter with Larry Bishop,
who has been hired to replace Ron Simpson as Triview manager but had not
officially started work.
Classic asks Donala for service estimates
Classic Homes has again asked the Donala district for cost
estimates for servicing the approximately 650 homes it intends to build on the
former Baptist Camp property. Duthie guessed that recent Triview tap rate
increases might have compelled the developer to ask for other figures.
Duthie told board members that recent tests indicated Donala
sewer lines were capable of handling the additional load should Classic request
inclusion. Classic representatives have made no further contact since the
district resubmitted its inclusion figures and cost-of-service estimates.
Holiday schedule changes
Duthie told board members that Donala would not receive final
tax income numbers until after Thanksgiving, and suggested the board postpone
its meeting until the week after the holiday. He said that the district
routinely met the last week of November, then cancelled its December meeting.
Board members tentatively agreed to the change.
The meeting went into executive session at 3:15 p.m. to
discuss the purchase, acquisition, lease or transfer of water, and personnel
matters.
The next regular meeting of the Donala board will take place
on Sept. 20 at 1:30 p.m. at the Donala office, 15850 Holbein Drive. Meetings are
normally held on the third Wednesday of each month.

Forest View Acres Water District, August
24: Board places property tax measure on the November ballot
By John Heiser
At its regular monthly meeting August 24, the Forest View
Acres Water District (FVAWD) board of directors approved placing a measure on
the November ballot. The ballot measure, if approved by district voters, would
impose a property tax mill levy of an estimated 37 mills on all properties in
the district.
Background
Management structure: The board consists of Rich Crocker,
Ketch Nowacki, Jeff Walker, Eckehart Zimmermann, and President Barbara Reed-Polatty.
Nowacki was absent. Reed-Polatty presided.
The district has retained Special District Management
Services, Inc. (SDMS) as its administrative manager. Lisa Johnson, SDMS district
manager, served as facilitator and secretary at the board meeting. Deborah
McCoy, President of SDMS, was also present.
Dan LaFontaine of Independent Water Services is the district’s
contract water operations manager. LaFontaine has submitted his resignation
effective Sept. 15. The district is seeking an operations manager to succeed
LaFontaine.
After LaFontaine leaves, Mike Bacon of Community Solutions,
Inc. (CSI) will be serving as the interim operations manager until a permanent
replacement is selected. McCoy is a part owner of CSI.
Water system: The district water supply consists of a
surface water plant and two wells, one in the Arapahoe aquifer and one in the
Dawson aquifer.
The water is treated with chlorine, pumped through 750 feet
of 6-inch water line, and stored in a 250,000-gallon steel storage tank. The
water is then distributed through 36,000 feet of distribution lines that vary
from 1 inch to 8 inches in diameter.
ASCG, Inc., the district’s engineers, have determined that
the water treatment facilities are in good condition, the water tank is in fair
condition, and the distribution system is in fair to poor condition. ASCG has
prepared a list of proposed improvements. (For the detailed cost breakdown see OCN
June 3, 2006, "Forest View Acres Water District, May 25: Board ponders
financing $6.2 million for improvements" posted at www.ourcommunitynews.org/v6n6.htm#fvawd).
The highest priority items focus on bringing the system into
compliance with state Health Department standards for chlorine contact time,
installing a looped pipe system to circulate water through the tank, additional
water storage to meet daily flow and fire flow requirements, and replacing small
and failing pipelines. Future improvements include work on the Dawson well,
improvements to the surface plant and water treatment facilities, and upgrading
or replacing the booster pump station.
ASCG estimated the total cost for all of the work at $6.2
million.
Operations manager transition
LaFontaine had submitted an invoice showing time spent
training Bacon as extra cost services.
Reed-Polatty suggested that his contract obligated LaFontaine
to train a successor.
LaFontaine replied that it was not required by his contract.
Crocker noted that LaFontaine had not performed some of the
services required by the contract.
The board approved Zimmermann’s motion that in exchange for
LaFontaine removing the additional charges, the district would overlook the
services not performed.
District operation proposals
Crocker reported that the district received proposals ranging
from about $60,000 to about $154,000 per year to operate the district.
CSI was the low bidder. McCoy noted that sealed bids were
used and CSI did not know the amount of the other bids before submitting its
bid. She credited CSI’s low bid to their knowledge of the district and its
operational needs.
Crocker and Reed-Polatty were designated as the district
representatives to negotiate with CSI.
Walker said, "I’m a bit concerned with having all our
eggs in one basket."
Proposed ballot measure approved
Reed-Polatty reported that one of the board members had
proposed that the ballot measure be tabled because it was not likely to pass.
Referring to ASCG’s list of improvements needed, Reed-Polatty
said, "Once it has been revealed to us that there are problems, we can’t
do nothing."
In response to a question from Crocker, McCoy noted that the
bond attorney and the bond underwriter will not be paid until the debt is
issued.
LaFontaine suggested that to improve the chances of passing
the measure, the district reduce the debt authorization from $8 million to $3
million to cover just the highest priority needs.
Zimmermann replied that the board would have to go back to
the voters for more money later to finish the improvements.
McCoy encouraged the board to obtain the maximum amount with
one ballot measure.
Crocker said, "Let’s go ahead with the election and
see how people feel. In my area, it is 50-50." He said, "The water
tank is 35 years old and hasn’t been checked for six to eight years. We don’t
have enough water to fight a fire." He added that using a mill levy is the
least expensive way to raise the money.
Zimmermann said, "We need to make clear what happens if
it doesn’t pass. I don’t want to hear [complaints] that the water bill just
went up $100."
Walker said, "I have faith in the residents that they
can make up their own minds."
The board announced that it will meet with the Shiloh Pines
homeowners association on Sept 10, 6 p.m., at the cul-de-sac at Lake Meadows
drive and with the Red Rocks Ranch homeowners association on Sept 11, 7 p.m., at
Tri-Lakes Fire Protection District Station 1.
Paul Rufien, the district’s attorney, noted that the board
members can provide information but cannot campaign or lobby at those meetings.
Financial matters
Johnson presented a list of claims paid through Aug. 24
totaling $38,383 that included $13,486 for ASCG’s services, $12,959 to SDMS,
$5,128 for electric and gas utilities, and $4,912 for LaFontaine’s services.
Zimmermann noted that the SDMS charges included 31 hours for
board meetings. He added that the costs are running considerably more than what
was budgeted.
McCoy replied that the district was not managed properly for
a long time. She said, "We are being prudent. You are going to come out on
top."
Reed-Polatty added, "The district is under-funded."
Referring to the cost of having mid-month meetings and
workshops, Rufien said, "You need to move toward a situation where the
mid-month meeting is not necessary."
Zimmermann noted that the electric bill is very high.
LaFontaine replied that the district operated much of the month on water from
the Arapahoe well. He added that the lack of a working Variable Frequency Drive
(VFD) increases the amount of electricity used.
Operations report
LaFontaine reported that during July, the district’s
surface plant produced 18,600 gallons, averaging 24 gallons per minute over 5.3
days. The district’s well in the Arapahoe aquifer produced 2.49 million
gallons, averaging 106 gallons per minute over 16.3 days. The net monthly
production was 2.67 million gallons.
Water sales for July totaled 1.81 million gallons.
LaFontaine calculated the net loss from the system during
July was 613,536 gallons or 25.2 percent of total system use.
LaFontaine reported that two leaking glue joints were
repaired July 7.
Bacon noted that improved alarm system and chart recording
equipment is urgently needed.
The board reviewed a proposal from Layne-Western to replace
the VFD at a total cost of $9,000. The proposal was approved subject to Rufien’s
review and approval of the contract.
LaFontaine reported that the installation of infrastructure
and preparation of as-built drawings for the Red Rock Reserve (formerly
Raspberry Ridge) development should be completed prior to Sept. 15. LaFontaine
said he is inspecting the installation.
Residents raise concerns
Scott Miller urged the board to work more cooperatively with
residents and look at the whole spectrum of alternatives, including dissolution
of the district.
Susan Gates asked that an accounting be provided at the next
meeting of the total amounts paid over the past year to SDMS, consultants, and
lawyers.
Gates asked if the forensic audit is available. Rufien
replied it can be released as a draft. Since it is a very large document,
Johnson asked those who want a copy to submit their request in writing and
approve the estimated cost.
Dan Spiegelberg noted that ASCG estimated about $153,000 for
outfitting the Dawson well, whereas Bacon estimated about $70,000. Spiegelberg
said, "I question all the other figures in the ASCG report."
Jeff Dull asked, "Why go after $8 million when you need
$750,000?" Johnson replied that $8 million is the authorization.
Anne Bevis expressed concern that the ASCG report proposes to
"fix everything at a huge price." She urged the board to reactivate
the technical committee so they can look for more cost-effective solutions.
Crocker said, "We have a responsibility to identify all
the needs. The biggest need is $1.9 million to add looping for fire
fighting." Noting that he had been on past boards that did not address the
problems, Crocker said, "We need to deal with it."
**********
The next regular board meeting will be held Sept 28, 5:30
p.m. at Tri-Lakes district Station 1, 18650 Highway 105 (near the bowling
alley). Board meetings are usually held on the fourth Thursday of each month.
Those wishing to attend should check the date, time, and location by calling the
SDMS at (800) 741-3254 or 488-2110.

Monument Sanitation District, August 15: Office
upgrade nearing completion
By Jim Kendrick
District Manager Mike Wicklund reported that the district
building renovation being performed by Access Construction was on schedule and
on budget. The district’s first phase of installing new sanitary sewer lines
under the streets of the east side of Wakonda Hills is also on schedule and on
budget.
Access Construction is remodeling the two suites next to the
current office to the south, which will become the new district office area and
conference room. The new roof, rain gutters, and front landscape drains are all
completed. The district was scheduled to move into its new spaces by the end of
August. The vacated district office will be remodeled for expansion of Shani’s
Café. The district installed a new grease interceptor under its east parking
lot on Aug. 28 to handle the increased size of Shani’s.
The board unanimously approved the appointment of CPA Nolan
Gookin to take over accounting for the Tri-Lakes Wastewater Treatment Facility.
The facility is owned equally by Monument Sanitation District, Palmer Lake
Sanitation District, and Woodmoor Water and Sanitation District. Woodmoor has
managed the facility for the other two districts as executive agent since it was
designed and built, but recently asked the other two districts to convert the
facility into a separate, independently managed entity by the end of 2006.
Facility manager Bill Burks will take over day-to-day operations from Woodmoor
District Manager Phil Steininger. Gookin will take over facility accounting from
Woodmoor office manager Hope Winkler.
The Monument board unanimously opposed Woodmoor’s proposal
that Mike Rothberg of engineering firm Rothberg, Tamburini, and Winsor
Engineering (RTW) be appointed co-manager with Burks. RTW designed and
constructed the Tri-Lakes Wastewater Facility and has been the consultant to
Woodmoor for facility engineering issues since then. The Monument board prefers
that Rothberg continue in his current status as the engineering consultant for
the facility, available to Burks as required for consultation on facility issues
after Burks takes over.
Wicklund reported that the town’s 36-inch stormwater drain
under Beacon Lite Road on the north side of the intersection with Highway 105
had become blocked and the road had begun to wash away during a recent
thunderstorm. Wicklund said that when he was notified by Monument Public Works
of the problem and the potential for serious damage to the district’s deeply
buried sanitary sewer collection line that passes through that intersection, he
directed the Wakonda Hills excavation contractor, J&J Excavating, to prevent
further damage. This contractor could respond far more quickly than the ones
normally called upon by the town. Wicklund said J&J would bill the district
for its repair of the town’s storm drain and he would bill the town for
reimbursement.
Wicklund said that this storm drain needed to be at least 60
to 66 inches in diameter to handle the increased stormwater flows that have
resulted from six years of town construction during a drought without
corresponding expansion of town drainage systems.
He noted that town stormwater drainage had also washed away
dirt supporting a district manhole for its major collection line along the east
side of the railroad tracks south of the intersection of Front Street and
Lincoln Avenue, behind Monument Addition No. 5. He added that stormwater was
starting to compromise the ballast for the railroad tracks as well, in a manner
similar to the damage caused to the east side of the railroad tracks south of
the southwest detention pond in Santa Fe Trails a few years ago.
Wicklund said he would have enough information to restate the
final months of the 2006 budget and would present a draft budget for 2007 at the
October meeting.
The board unanimously approved resolutions for inclusion of
six Wakonda Hills properties and one other in Colorado Estates.
The board authorized Wicklund to have engineering consultant
GMS, Inc. research possible grants for subsidizing the Wakonda Hills collection
system installation. There are numerous federal and state grants for
rehabilitation of aging neighborhoods with failing septic systems such as those
in Wakonda Hills. Layers of clay under the soil in some steeply sloped areas
like Wakonda Hills can carry sewage from clogged septic systems downhill to open
surface areas that have been exposed by erosion. The sewage can then flow
downhill on the surface to enter a well head and contaminate its domestic
drinking water. The Colorado Department of Public Health and Environment is
encouraging communities like Wakonda Hills to abandon their failing septic
systems and create or seek inclusion into a sanitation district.
The meeting adjourned at 5:03 p.m. The next meeting will be
at 4 p.m. on Sept. 20, in the Monument Sanitation District’s new offices on
Second Street. Meetings are normally held the third Tuesday of the month.

Tri-Lakes Wastewater Treatment Facility Open
House, August 12: Facility shows off new capabilities
By Jim Kendrick
Facility Manager Bill Burks and staff members Scott Eilert
and Toby Ormandy hosted an open house in the laboratory and administration
building that was built by Access Construction. Burks said the purpose of the
open house was to show the completed facility’s new capabilities to board
members, district managers, employees, and their families, as well as interested
residents of the three owning special districts, the Monument, Palmer Lake and
Woodmoor sanitation districts.
After treating everyone to hamburgers, hot dogs, chips, and
sodas, Burks conducted a tour of the new building’s upgraded laboratory,
office complex, equipment control room, conference room, and break room. The
tour included visits to the equipment building’s maintenance and treatment
machinery areas, map/documentation rooms, and ultra-violet disinfection room, as
well as the aeration basins, clarifiers, and sludge lagoon.

Triview Metropolitan District, August 23:
District considers loan allocations
By Elizabeth Hacker
This was the final board of directors meeting for departing
District Manager Ron Simpson before Larry Bishop takes over the manager’s
duties. Board member Martha Gurnick was absent.
Simpson reported on the status of the ongoing issue with the
district’s bond council to finalize the allocation of funds from the loan the
district is pursuing from Compass Bank, the impact fee structure proposed by Red
Oak, and land dedication for trails or open space.
$36.7 million loan application
Simpson said that the letter of intent to borrow $36.7
million at 6 percent interest had been signed and that the district’s bond
council was now evaluating the categorical allocation as part of the application
process. One of the concerns of the bond council is the cost of issuing the
loan. This cost and the final allocation to categories including repayment of
bondholder debt, roads, water, sewerage, drainage, parks, and mosquito control
must be finalized. The board expects to work these out before October, at which
time they intend to sign the loan.
Impact fees
Simpson had circulated a memo to the board that addressed the
impact fees they had adopted that went into effect Aug. 1. Simpson noted that he
had discussed the fee structure with Dale Turner of Home Place Ranch, Mike
Raider of Promontory Pointe, Joe Loidolt and Jim Boulton of Classic Homes, Kevin
Burnett of Red Oak, Steve Stephenson, and attorney Pete Susemihl. Several issues
were not thoroughly considered when the impact fees were adopted—in
particular, how to address compensation to developers for capital improvements.
The impact fee was adopted to cover cost of infrastructure improvements and not
operation and maintenance. If infrastructure improvements are made by the
developer at their cost, an impact fee for these improvements is essentially
charging the developer twice. Simpson suggested the logical solution would be to
reimburse or credit the impact fee for a specific function in the amount equal
to the cost for improvement constructed by the developer. Simpson used the
example of a 200-lot residential subdivision that as of March 1, 2007, would owe
$320,000 in drainage impact fees. If the developer’s cost to install drainage
improvements on the property is $400,000, the most that would be credited to the
property is $320,000. However, if the improvements were less than $320,000, say
$200,000, the difference ($120,000) would be charged as an impact fee. Because
fees are collected at the building permit phase, the improvements should be made
before a permit is issued. In his memo, Simpson recommended that the board
modify its position on the adapted impact fee structure.
Attorney Susemihl questioned if the issue was that the fees
were so high as to be a deterrent to growth, to which Simpson responded that it
was a concern but the issues he was addressing was the double charge for
infrastructure. He added that often developers prefer building portions of the
infrastructure, particularly roads, parks, and drainage improvements, and having
no way to credit the impact fee for these improvements would discourage them.
Kevin Burnett of Red Oak responded to a question by the board
that the fees were calculated based on the current cost for infrastructure
installation. The board took action to put the impact fee structure on hold
until a solution could be worked out that addressed the double-charge issue and
directed Simpson to inform developers who have built or are building
infrastructure improvements that they will not be charged twice.
Board accepts trail easements
Simpson reported that a north-south 50-foot-wide strip of
land about one-half mile in length between the Heights at Jackson Creek and the
proposed Promontory Pointe subdivision (east of the Heights) would be brought
into the district at a cost of $235,000. He said the 50-foot-wide strip would
provide an alternative location to the proposed adjacent 30-foor-wide trail
easement to the east. The 50-foot width also works well for the district because
it is wide enough to provide for drainage, utility line stacking, and room for
their maintenance vehicles. Simpson said this strip could also serve as a future
location for a well.
The 30-foot-wide trail easement runs along the entire western
boundary of Promontory Pointe, from Baptist Road to trail’s entrance into Home
Place Ranch. Most of this 30-foot easement is formed by the rear 30 feet of all
the residential lots that back up to the western boundary of Promontory Pointe.
Simpson noted that he had some discussions with the Heights
Homeowner’s Association (HOA) about the northern portion of the 30-foot-wide
trail easement strip. from the 50-foot strip between the subdivisions.
Simpson pointed out that another Triview easement in the
Heights could be used as an alternative trail connection and that Triview
already maintained it. He suggested that 30 feet was not wide enough to serve as
a utility easement, and that it was redundant since there was already another
50-foot easement in the subdivision that could be used as a connection to Home
Place Ranch. He said he was concerned about the district’s ability to maintain
the 30-foot-wide strip in Promontory Pointe to HOA standards.
In response to Simpson’s report, Heights HOA President
Robert Fisher voiced the HOA’s strong opposition to not continuing the trail
in the 30-foot corridor an additional one-fourth mile along the property line
between the Homestead and Promontory Pointe to their common boundary with the
Home Place Ranch subdivision. Fisher said that if this northern segment of the
30-foot trail easement was deleted from the plat and PD site plan, area
residents would forever lose the opportunity for a continuous trail connection.
He strongly urged the board not to abandon this one-time opportunity.
The board then considered a number of alternatives for the
30-foot strip. Board President Steve Stephenson expressed concern that a
corridor would not be maintained by Triview and that it might turn into a weed
patch. He suggested that if it were platted as a larger lot, the property owner
would maintain it and save the district taxpayers’ dollars. In response,
Director Steve Belzer noted that trail corridors were important, that it could
be planted with wild flowers or trees, and that the district discouraged
watering large lawns so it may turn into a weed patch anyway. Susemihl suggested
that the board could accept the strip into the district but not commit to a
purpose for it. The board voted to accept the 50-foot and the 30-foot strips of
land.
Baptist Road widening
Simpson reported that the district is being assessed $7,200
for a drainage improvement that wasn’t included in the plans. He suggested
that even though the omission was not the district’s fault, it should pay for
the improvement because it was needed. The board voted to approve an amount not
to exceed $7,200 for the improvement.
Wastewater treatment facility
Chuck Ritter of Nolte Associates reported that the Upper
Monument Creed Regional Wastewater Treatment Facility construction was
proceeding but that the contract for the equalization basins was a month behind
schedule.
(See the Donala article for
additional news on upgrade construction at this facility.)
Common land use standards:
Ritter reported that he would meet with town officials the
following week to consider common street standards. He requested that Simpson
and Larry Bishop be present at that meeting. In response to Stephenson’s
question about who is paying for updating the street standards, Ritter said that
the town would cover this portion of updating the standards.
District operations and maintenance manager Steve Sheffield
reported that the new water meters were in and that he would be replacing some
of the older meters that were not working.
He asked the board to approve $8,000 for a perforated PVC
drainage pipe to collect run-off in Bridle Ridge. The board asked if he was sure
it was run-off, to which he replied that the water did not have chlorine in it
and followed the outside of the pipe, so he was quite sure it was. They approved
funds for this drainage improvement.
Attorney’s report
The board unanimously approved and signed petitions for
inclusion into the district from the developers of Promontory Pointe, Sanctuary
Pointe, and Home Place Ranch.
Financial report
District administrator Dale Hill reported that four new
permits had been issued, two under the new fee structure. She noted that they
had entered into an intergovernmental agreement with El Paso County for the
November election to "de-Bruce" all sales taxes for 10 years, and that
she had been appointed the election official. Stephenson asked if the wording
had to be so "legalese." Simpson asked Heights HOA President Fisher if
the group would support this measure, to which he responded that he did not like
the wording and had seen examples that were more palatable. Hill and Susemihl
said this was wording developed by Wysor and had to be into the state in a few
days. Fisher said he would try to find better examples and get them to the board
as soon as possible.
The meeting adjourned at 6:30 p.m.

Triview Metropolitan District, August 30:
Board approves ballot measure
By Elizabeth Hacker
To de-Bruce or not to de-Bruce? That is a question voters of
the Triview Metropolitan District will decide on Nov. 7. Their board of
directors, Martha Gurnick, Chuck Burns, Joe Belzer, and Steve Stephenson, met
Aug. 30, to review the wording of the ballot initiative. Director Julie Glenn
did not attend. District resident Robert Fisher, attorney Pete Susemihl, and
staff Ron Simpson, Dale Hill, and Larry Bishop were also at the meeting to
review the ballot wording.
Board president Stephenson emphasized the reason for placing
the question to voters was to pay down the district’s debt in 10 years. He
noted that the district could do this if they were allowed to retain sales tax
revenues instead of being obligated to return it to the retailer as required
under the TABOR amendment to the state Constitution. He emphasized that it would
not increase property taxes, and the statute of limitations was 10years.
Robert Fisher questioned the language regarding the 5.5
percent property tax revenue limits and said it was confusing and would be
interpreted as a property tax increase. In response, Stephenson agreed that it
was confusing but said the language specifically addressed the "growth +
inflation = 5.5 percent" calculation enacted as part of TABOR. He added
that if approved, the initiative would not increase taxes or the mill levy.
Simpson added that the district did not project any mill-levy increases in the
future. Fisher acknowledged that it was the county that assesses property values
every two years and collects property taxes, not the district. Stephenson added
that the mill levy could decrease once the debt was paid.
After a discussion about how important it was for the board
to meet with the residents to explain the ballot, the board unanimously approved
Resolution 08-2006, which included the language for Ballot Issue 5 and directed
staff to send it to the county for the Nov. 7 election.

Triview Ballot Issue
Commencing January 1, 2007 through December 31, 2017, shall
Triview Metropolitan District (without increasing existing tax rates or imposing
a new tax) be authorized, for the principal purpose of paying down the District’s
debt sooner, to collect , retain, and spend as a voter approved revenue change
pursuant to article X, Section 20 of the Colorado Constitution and regardless of
the provisions of any other law, including without limitations the 5.5% property
tax revenue limit of 29-1-301, C.R.S,
-
All revenues accounted for in the District’s general
fund such as property taxes, specific ownership taxes, sales taxes, property
taxes and other revenues received from the town of Monument, impact fees,
grant revenues, and investment income, and
-
In any year in which the District’s water and sewer
utility does not qualify as an enterprise, revenues accounted for in the
enterprise fund, such as water and sewer user fees, tap fees, inclusion
fees, water reuse fees, grants, and investment income?

Woodmoor Water and Sanitation District,
August 10: District will serve new high school
By Sue Wielgopolan
Woodmoor General Manager Phil Steininger confirmed at the
board’s Aug. 10 meeting that the site chosen by Lewis-Palmer School District
38 for their new high school lies within Woodmoor Water and Sanitation district
boundaries, and the district will provide service. After the contentious
potential location on Wissler Ranch was abandoned, the school board selected the
property off Monument Hill Road as best suited to meet its requirements.
District 38 has contracted with Pinewood Farms to purchase
the 40-acre tract, as well as about 25 acres from Bill Herebic of Monument
Gateway Investments. D-38 also intends to buy five additional acres on Lot 5 of
the Williams Ranch from Roger Williams. Rumors that D-38 may be negotiating for
an additional 13 acres from the Greater European Mission remain unconfirmed.
Purchase of the properties is contingent on passage of a district-wide bond
issue in November.
Herebic had intended to build about 65 single- and
multi-family homes on his property, which was to be named Hillsong Village. The
sale of the tract to D-38 will result in a significant reduction in sewer and
tap fees for the Woodmoor district.
Herebic had reserved excess water for his development.
Steininger told board members that water agreements are attached to the
property, not the seller. As a result, the school district will be able to
purchase the amount of excess water agreed upon in Herebic’s contract at the
price he originally negotiated, which is lower than the price the district would
have paid at current rates. D-38 will still have to pay tap fees.
District revises 2006 income expectations
Steininger reviewed the 2006 budget with the board, comparing
anticipated income and expenditures with actual figures. In several categories,
income for the year to date was significantly lower than expected. He told
members that although official budget revisions would not be filed with the
state until after final figures were in at the end of the year, the board needed
to reallocate funds to cover unexpected well repairs and reprioritized projects.
Steininger told the board that higher than anticipated
expenses and delayed collection of water and sewer tap fees resulting from
lagging construction schedules accounted for most of the discrepancies.
Annexation fees were also below expectations.
Three wells needed repairs in 2006. Woodmoor staff had
requested an allowance to cover one well repair, which is usually adequate.
Additionally, the amount spent on land acquisition for wells and other district
projects was more than estimated.
Though the rise in interest rates contributed $30,000 more to
the district’s coffers than expected, and miscellaneous income from Mountain
View Electric Association credits and late penalty collections were higher than
originally estimated, the total was insufficient to offset the shortfall of
about $750,000.
Steininger proposed adjustments to the budget to avoid an
increase in expenditures, pushing some projects to the forefront and postponing
others. The board voted to approve the revisions.
New wells to be completed in early 2007
District engineer Jessie Shaffer reported that Well 20 was
still in the land acquisition phase. Several years ago, the prospective sellers
combined the proposed well lot with an adjoining lot to form a larger parcel.
Now Woodmoor must go through the subdivision process with El Paso County to
re-establish the vacated lot line.
Shaffer has submitted final documentation to the El Paso
County Planning Commission for approval. The hearing is on the September
calendar for the Planning Commission and the county Board of Commissioners,
which must approve the plat. The district hopes to close on the property in
September.
Bishop and Brogden have the drilling contract bid forms and
ad ready, and drilling could begin as early as October, with pipeline connection
excavation to follow.
County stormwater fees discussed
The issue of whether or not the Woodmoor district is
responsible for paying drainage impact fees to the county for impermeable
surface area created by the new well and its associated structures arose during
discussion of fees and permits. Woodmoor’s attorney, Erin Smith stopped the
conversation, and told the board to reserve further discussion for executive
session.
In executive session, Smith advised members that state law
exempts special districts from paying such fees.
Board moves ahead with Maguire property inclusion
The owners of three vacant parcels on the north side of
Highway 105 across from the Village Center at Woodmoor have requested that their
properties be included in the Woodmoor Water and Sanitation District. Though Jim
and Donna Maguire have no immediate plans for development, they would like to
ensure future water and sewer service from Woodmoor.
President Jim Taylor conducted a public hearing on the
inclusion, but there was no public comment.
In outlining the pros and cons of the proposal, Steininger
told the board that long-range plans anticipated the eventual inclusion of the
Maguire’s property, which is completely surrounded by the district. The
previous owners had negotiated rights for four water taps in exchange for
utility easements across the land, which were transferred when the Maguires
purchased the parcels. Steininger pointed out that service would be relatively
easy to provide, because district water and sewer mains bisect the area.
In response to questions from the board, Steininger verified
that the current owners held no surface rights to Dirty Woman Creek, and that
inclusion fees would not be paid until the sites were developed.
Woodmoor staff recommended that the board move ahead with the
inclusion. After members voted to proceed, Smith said she would prepare a draft
resolution for inclusion to be presented at the next meeting.
Joint Use Committee open house
Jim Whitelaw, acting as Woodmoor’s alternate to the Joint
Use Committee (JUC), told the board that the Aug. 8 meeting was sparsely
attended. The committee includes delegates from the boards of the Monument and
Palmer Lake Sanitation Districts and Woodmoor, which co-own the Tri-Lakes
Wastewater Treatment Facility. Plant manager Bill Burks and executive agent Phil
Steininger also are on the committee.
Committee members finalized plans to host an open house Aug.
12 at the new office/lab building, which was completed in late 2005. Committee
members approved the purchase of a grill, which would later be used by plant
staff.
The JUC also continued to refine protocol for the plant’s
conversion from contract management by the Woodmoor district to a self-managed
facility, and authorized Woodmoor to assemble the necessary paperwork
documenting the process.
Wells 11 and 15 back on line; broken hydrants being replaced
Operations manager Randy Gillette reported that Wells 11 and
15 were again operational. The Well 11 pump was lowered on recommendations from
consulting firm Bishop and Brogden in order to bring yield back up to the
previous level of 200 gallons per minute. Well 15 was initially pulled from
service due to check-valve failure on the motor. After reviewing their options,
district staff opted to proactively lower the pump as well as install a smaller
diameter drop pipe to increase pumping velocity and reduce sediment settling.
Gillette said that Well 2, which has been a consistent
producer for the district for many years, finally "gave it up." When
the pump was pulled, the crew found that the drop pipe needed replacement.
Technicians also inspected the well interior with a television camera to look
for corrosion and ensure that the casing could withstand the planned wire brush
cleaning. Gillette said Woodmoor plans to keep the pump at the same depth.
Well 2 taps the Dawson aquifer. Though the Dawson is the
shallowest of the four aquifers underlying the Tri-Lakes area, it had yielded a
low but reliable 45 gallons per minute for decades. Because Dawson wells have
traditionally "held up" for the district, Woodmoor chose to repair
rather than abandon the well.
Woodmoor is replacing six fire hydrants, including three that
are out of service. Lack of manpower and difficulty in obtaining new hydrants
from the manufacturer has slowed the operation. The district contracted Nordic
Excavating to complete the work, which Gillette expected to be finished by the
end of August.
Elizabeth Hacker asked about the significance of the
differently colored tops on the hydrants. Gillette responded that each hydrant
was color-coded according to pressure, so that a fire crew would know what to
expect when hooking up to the water supply. He told members that the district
had contracted with the Tri-Lakes Fire Protection District to paint the
hydrants.
Woodmoor continues sewer pipe lining program
Gillette told the board that TEC would resume lining the
sewer mains. The PVC liner is inserted inside the older cracked clay pipes,
providing an impermeable plastic interior at a considerably lower cost than
excavation and replacement.
The contractor will be working in Zone 5 of the district.
Woodmoor hopes to complete video inspections of all its sewer pipes and line
those showing significant damage in three to five years.
Gillette applauded the efforts of Lance Nielson for keeping
the TV cameras running and completing inspections on time, enabling TEC to meet
its schedule.
Meter replacement program hits halfway mark
District engineer Jessie Shaffer reported that technicians
had installed about 1,600 meters, roughly half the total number scheduled for
replacement. The process is moving ahead smoothly. Shaffer expects to complete
the project by the end of 2006.
Development update
Rocky Mountain Custom Wood Structures has submitted plans to
build a new commercial office park on six lots north of Colorado Heights Camping
Resort and south of County Line Road on Monument Hill Road. Woodmoor is
reviewing the plans for the development, which will be called Woodmoor Vista
Office Park. The developer hopes to begin construction within two to three
months.
Sam Schoeninger of Alexandria Corp., the developer of Lot 27
of Misty Acres Filing 2, has almost finalized plans for 42 patio home sites and
is working with El Paso County on road design and location.
Woodmoor contractors must verify employees’ legal work status
Smith informed board members that a law that forbids local
government contractors from employing illegal aliens applies to the district.
Smith created a contract that places the burden of verifying worker
documentation and legal status on any contractor hired by Woodmoor. The contract
also specifies penalties for violations.
The Woodmoor board voted to add a clause to the district’s
rules and regulations requiring all contractors working for the district to sign
and abide by the document’s provisions.
The board went into executive session to receive attorney
instruction regarding negotiations for water rights, to discuss county permits
and fees related to construction of a new well including fees related to
stormwater, and to discuss personnel matters. The Woodmoor board also was
scheduled to meet for a special executive session, Aug. 24 to continue
discussions on negotiations for water rights acquisition.
The next regular meeting of the Woodmoor board will take
place Sept. 14 at 1 p.m. at the Woodmoor office, 1845 Woodmoor Drive. Meetings
are normally held the second Thursday of the month.

Donald Wescott Fire Protection District,
August 16: Board renews insurance policy with VFIS
By Jim Kendrick
Directors Joe Potter and Kraig Sullivan were excused.
Allen Cook of T. Charles Wilson Insurance Co. and Mickey
Leonard of VFIS Insurance Co. each gave half-hour presentations on proposals to
provide a year’s worth of coverage when the current VFIS policy expires. Each
offered property, automobile, malpractice, and employment practices liability,
plus an umbrella policy for coverage in excess of the usual limits of the
regular policy.
Wescott currently has an accident and sickness insurance
policy with VFIS, which was renewed last year for a period of three years. VFIS
also provides Wescott’s workers compensation policy and life insurance
policies. The board unanimously approved renewal of the VFIS policy based on
this company providing training that leads to policy discounts, level of service
over the past several years of VFIS coverage, and no significant difference in
cost between the two companies’ proposals. Renewal of the VFIS liability
policy will cost $14,813.
Treasurer’s report
The overtime budget may appear to be slightly overspent for
this point in the year but is actually in line with historical norms due to the
increase in vacations during the summer.
Treasurer Dave Cross informed the board that the auditor had
completed his portion of the 2005 report and was waiting for a letter from the
department’s attorney that is required for submitting it to the state. The
auditor reported that the department is using sound accounting procedures and
policies.
Cross reported that the district was ready to sign the loan
agreement for lease-purchase of the new pumper engine. He noted that at least 10
percent of the $330,000 loan from Wells Fargo Bank needs to be spent within six
months of the loan’s origination. He suggested early equipment purchases for
the new engine to help use the first $33,000 of the loan. The district has made
some minor changes in the engine’s specifications, adding some features and
dropping others, since the manufacturer submitted the winning bid of $321,000.
The final cost should not change significantly
Chief’s report
Assistant Chief Vinny Burns reported 97 total runs for the
month of July, of which 72 were in the district and 25 were automatic-aid or
mutual-aid calls. Total runs for the year are at 618.
Chief Jeff Edwards advised the board that Ford had completed
wiring harness and exhaust system repairs on AMR’s ambulance 718 and the
vehicle was back in service at the Gleneagle Drive station.
Edwards reported that the annual pump and hose tests for the
engines had been completed. The ladder test was scheduled to be completed in the
next week. He said Wescott had also assisted Black Forest with its pump tests
for the Insurance Services Organization certification. The district’s
Firefighter I class has been completed as well.
Edwards and Burns attended a budget writing class.
Firefighter Curt Leonhardt completed a fire apparatus mechanic class. Volunteer
firefighter and personal trainer Mike Forsythe gave a presentation on physical
fitness to full-time personnel and volunteers. He is director of the district’s
physical fitness program.
Edwards also noted that the department will participate in
the Muscular Dystrophy Association’s "Fill the Boot" telethon, with
firefighters posted at certain locations throughout the area to raise money for
the fund.
The board asked Edwards to give them an update at the
September meeting on performance evaluations, the preliminary 2007 budget, and a
list of needed equipment purchases, plus a "wish list" of possible
expenditures.
The next regular meeting was changed to Sept. 27 due to board
members being out of town on Sept. 20 for the annual Special District
Association Conference.
The meeting adjourned at 8:50 p.m. The next meeting will be
at 7 p.m. in the conference room of Station One, 15415 Gleneagle Drive. Meetings
are normally held on the third Wednesday of the month.

Tri-Lakes Fire Protection District, August
24: New ambulance on the way
By Lee Colburn
With all directors present, President Charlie Pocock called
the meeting to order. Rick Barnes, John Hildebrandt, Keith Duncan, and John
Hartling, along with Battalion Chief Bryan Jack and Fire Chief Robert Denboske,
were in attendance at the August Tri-Lakes FPD meeting.
Financial report
The first new topic covered was the financial report by
Treasurer John Hildebrant, who outlined the department’s progress. Closing out
August, the budget was within 5 percent over projections. Continued increased
expenses associated with Station 2 made up most of the overage. This was due to
station repair bills from previous grounds maintenance. All directors were
pleased with budget progress.
Ambulance vehicle inbound
Fire Chief Denboske said the new ambulance will be delivered
in November and will need to be outfitted with equipment from the old 2282
ambulance vehicle. Following this, the new unit will need official certification
before becoming operational. Pocock said the department might need to break out
ambulance crews as a separate function from the cross-trained firefighters. Once
the department is up to three vehicles, the ambulance service would be the
second largest in the county. Also, $11,000 in computer equipment will accompany
the ambulance purchase, which was funded by part of a grant.
Station 2 problem unresolved
The water situation with Station 2 remains under
investigation, according to Rick Barnes. Further investigation is planned, but
the well is not leaking. Nearby on Rollercoaster Road, there appear to be
artesian well issues. The station’s septic system is also under investigation.
Recent groundwater levels continue to be monitored and are a point of concern.
Third-party billing
The board discussed and passed a motion to forgo renewal of a
third-party billing contract that was up for October consideration. Instead, the
contract will expire and the department will negotiate a consultant contract
under Denboske’s direction.
Tax increase ballot measure and impact fees approved
The board passed a motion to recommend approval of an impact
fee proposal that would charge builders $700 per new dwelling or $700*
per
2,000 square feet in a commercial project. Pocock stated that this fee would
help offset the growth that the Tri-Lakes district is anticipating. The next
step would be to formulate the collection strategy with the Town Council and
Planning Commission. The board passed, 4-1. the proposal to ask in the November
elections for a 1.5 mill levy increase, from 7.0 to 8.5 mills. Denboske was
named the election official for this issue. (* This figure was incorrectly
stated as $7,000 per 2,000 square feet in the printed paper).
The meeting adjourned at 8:10 p.m.
**********
The Tri-Lakes Fire Protection District board normally meets
the fourth Wednesday of each month. The next meeting is scheduled for 7 p.m.
Sept. 27, immediately preceding the Tri-Lakes-Monument Fire Authority board
meeting at Tri-Lakes district station 1, 18650 Highway 105 (near the bowling
alley).
For more information, call Chief Denboske at 481-2312 or
visit www.tri-lakesfire.com.

Woodmoor/Monument Fire Protection District,
August 23: Firefighters praised for work on Station 3 remodel
By Susan Hindman
Renovations for Woodmoor’s Station 3 are mostly complete,
and Battalion Chief Mike Dooley announced it’s "ready for
inspection." Directors Rod Wilson and Si Sibell were absent from the board
meeting of the Woodmoor-Monument Fire Protection District.
Dooley congratulated all the firefighters—from Stations 1,
2, and 3 and all shifts—who did the renovation work, saving the district a lot
of money. He added "kudos" to Battalion Chief Greg Lovato, who did a
lot of the construction and framing with his own tools, and firefighter Kristian
Naslund, who used his own equipment to paint the bay floor.
The station received new windows, carpeting, tile flooring,
rubber matting for the exercise room, beds, and recliners. In addition, the bunk
room now has separate male-female sleeping areas, the bay floor was painted, and
heating repairs were made.
Dooley said the work—which totaled $21,311—went over the
original estimate by $346, and he presented the board with a letter giving a
breakdown and explanation of the added expenses.
Board members added their praise and thanks to all. Treasurer
Bob Hansen suggested the board do something special for the firefighters, and
directors approved spending up to $700 for a barbecue that would include the
workers and their families.
Hansen’s treasurer’s report noted that the district is
operating at around 6.7 percent under budget. Instead of the projected spending
of $103,305 a month, $96,329 has been spent.
With property tax revenues and specific ownership taxes
collected so far, and interest income generated, the district’s three bank
accounts total $1,075,335.
Hansen said he caught an error in the amount the district had
received for firefighter inspection revenues. Woodmoor should have received
$3,375 for the work, but only got $1,215. The remainder had been directed to the
Tri-Lakes Fire Protection District’s account. That has now been corrected.

Tri-Lakes-Monument Fire Authority, August
23: Auditors expenses questioned
By Lee Colburn
The Tri-Lakes-Monument Fire Rescue Authority convened its
August 23 regular meeting at 8:20 p.m. with a full board and many observers.
Treasurer John Hildebrandt reported that the district is
about 2 percent over budget, and he said he was satisfied with the spending
rate. Tri-Lakes Station 2 maintenance issues and differing deposits to the two
sub-districts were reasons for the spending deviations. Current revenues are
generally on target for the projections.
Driver-Engineer award
Monument Fire Protection District Capt. Curtis Kauffman
awarded three firefighters the special rating of Driver Engineer in a station
meeting room ceremony in front of wives, parents and department personnel.
Firefighters Mike Keough, Ryan Graham and Lisa Frasca were awarded their Driver
Engineer’s badges after successfully completing a Colorado Fire Safety Course.
The firefighters successfully passed a nationally certified exam, followed by a
practical driving test.
Auditor discussion
Board President Tim Miller opened a thorough discussion
concerning issues surrounding the services of independent auditor Gordon,
Hughes, and Banks. The authority was presented with an invoice well over the
original agreed price quote of $14,500 for services rendered during the recent
audit. Two additional bills totaled approximately $10,000 in unanticipated
overruns. After confirming that none of the additional expenses were
communicated to the board during the audit, the board first voted to decline
paying any bills over the $14,500 figure. Then board members directed the
department to get an itemized listing. The possibility of employing the firm in
future consulting and auditing support was tabled pending further investigation.
Administrative assistant hired
The board discussed and decided on the hiring of a part-time
administrative assistant as a replacement for the current contract
administrative help, which would cease by the end of September. The board also
discussed a proposal for increasing the current administrative position to full
time. Members decided to discuss this proposal in a future special session.
Personnel policy manual changes
Battalion Chief Bryan Jack presented proposed policy manual
changes that the department membership committee created for adoption. The minor
changes involved harassment policy rewordings for clarity and revisions to the
hiring policy posting. The board accepted the proposed changes.
Executive session rule change
A recent administrative ruling concerning executive sessions
will require the board to record all executive sessions closed to public
observation. The audio recordings must be secured by a designated member of the
board and kept for 90 days before purging.

Fox Run Regional Park master plan
update open house, August 29: Park plan receives favorable comments

By Jim Kendrick
The El Paso County Parks Department held an open house at
Pavilion 4 of Fox Run Regional Park to present the interim results of written
survey responses submitted by 178 citizens on the department’s draft update of
the park’s master plan. The open house was hosted by Director Tim Wolken,
Planning Division Supervisor Neil Katz, Park Planner Brian Kay, District I
Supervisor Ken Gerber, Maintenance Division Manager Jerry Westling, and Fox Run
Regional Park Maintenance Director Bill Campbell.
About 100 citizens attended the session and all were greeted
and engaged by staff members who asked them questions and showed them what each
of the displays depicted.
Wolken said he was very pleased with the turnout at the
pavilion and the uniformly positive comments of the survey responses on the
current status of the park. Survey comments indicated preferences for improved
rest rooms and expansions of the trail system, open areas, playground, roads,
and parking, as well as new horse trailer facilities and an unleashed dog area.
Phase I infrastructure improvements
-
New Baptist Road Trailhead with parking for vehicles,
horse trailers, restrooms, signage, and a link to existing trails ($30,000)
-
Restrooms/warming hut on the southeast side of the lower
lake ($200,000)
-
Additional parking for 50 more cars south of Oak Meadows,
the open space at the southeast corner of the park ($20,000)
-
New playground to replace existing wooden equipment at
Oak Meadows ($70,000)
-
New water line to improve service for all park facilities
(funded separately)
Phase I trail improvements
-
Ridge Entrance Trail – add 4,200 feet of Tier II trail
($2,000)
-
Sun Hills Entrance Trail – add 2,000 feet of Tier II
trail ($1,000)
-
Stella Entrance Trail – add 4,000 feet of Tier II trail
($2,000)
The proposed cost estimate for Phase I is $325,000 .
Phase II infrastructure improvements
-
Upgrades of two restrooms to potable water for hand
washing and drinking, and leach fields ($120,000)
-
Dog park for unleashed walking in 5 acres of fenced area
at southeast corner by intersection of Stella Drive and Roller Coaster Road
($25,000)
-
Additional parking for 25 cars at the new dog park
($16,000)
-
Improved access at Roller Coaster Road ($50,000)
Phase II trail improvements:
-
Park trail addition— add 5,300 feet of Tier II trail to
perimeter loop trail ($3,500)
-
Park trail addition—add 3,300 feet of Tier II trail to
connect ponds to Pine Meadows ($2,000)
-
Roller Coaster addition—add 5,300 feet of Tier II trail
to connect Roller Coaster Road parking and add perimeter loop trail ($3,500)
The proposed cost estimate for Phase II is $220,000.

Woodmoor Improvement Association Board,
August 16: Board approves matching funds for fire protection grants
By Chris Pollard
Speeding on Moor Drive
Two Woodmoor residents came forward to express their concerns
about speeding and aggressive driving on the north end of Moor Drive. It is
posted with a 25 mph limit, but they said they had observed many delivery and
service trucks and a school bus driving at speeds obviously higher than this. At
night the road appears to be used as a detour around the weigh station by semi
trucks, and in the early morning an occasional car or two speeds by. They asked
why Doewood Drive was not available as a through street as it appeared to have
been one previously.
Kevin Nielsen, chief of Woodmoor Public Safety, said that
Doewood was never intended to be a through street but was made into one when an
adjacent development, Doewood Estates, was under construction. Subsequent
lobbying by people on the street reclosed it after the construction was
completed.
With regard to the speeding, Nielsen recalled that
measurements with the WIA speed trailer had shown occasional speeding up to 70
mph. He suggested they should call the Sheriff’s Office about speeding
vehicles and the State Patrol with regard to trucks that were avoiding the weigh
station.
Wang named as NEPCO representative
Todd Wang, who has been a Woodmoor resident for four years,
was appointed by the board to be a representative for the WIA on the NEPCO land
use committee. The board had been looking for somebody with an understanding of
civil engineering plans and projects and Todd had volunteered.
Wang said that he had been in the Army Corps of Engineers for
many years and had been involved in several construction projects, including
local studies on Fountain Creek. He said he had many dealings with other small
communities and government organizations on flood control and experience working
with developers and builders. He was now transitioning into the private sector.
Support requested for Sheriff’s Budget Request
Bill Walters, vice president, said that the county has a
problem with its budget. The sheriff needed money to expand the jail to meet
obligatory requirements but traffic patrol money, on the other hand, is
discretionary. He said that the northern part of El Paso County has already
experienced considerable growth and the Town of Monument has given planning
approval for projects that would add several hundred homes south of Higby Road.
Clearly, this showed a need for funding extra patrols to cover this. He said
that the WIA should make the case to Wayne Williams, county commissioner, that
there should be a budget increase for additional services needed to cover the
additional growth. Walters was not clear where the commissioners were in
approving the budget but suggested that the WIA should send a letter to Williams
supporting the budget increase. Currently, the Sheriff’s Office is talking
about reducing hours rather than increasing them. Although a good proportion of
the growth has been within the Town of Monument there is still extra growth in
the unincorporated areas.
Jim Woodman, director of Forestry, suggested that the letter
to Williams should ask that service to the Woodmoor area be maintained at
current levels.
Overview of high school meeting
Hans Post, president, gave a short overview of the meeting
between Lewis-Palmer School District 38 and Woodmoor residents. (See article
on Aug. 7 meeting) Main issues mentioned included traffic and other
potential nuisances, plus communication and funding. Post said there had been
little feedback to the WIA after the meeting and thought there was not enough
information available at the moment to make further decisions. He added that he
had checked with the county Department of Transportation about speculation on
the future of the Monument Hill frontage road and confirmed that there was
sufficient space to widen I-25 and the frontage road including space for
expanded junctions. The Transportation Department noted that the school district
needed to include enough money in its bond issue to cover off-site improvements.
Grant applications for Community Wildfire Protection Program
Woodman proposed that the board allocate extra funds for a
major new program related to the Community Wildfire Protection Program. The
State Forestry Service had asked the WIA to submit a request for grant money
from an $8 million fund set up for mitigation programs. A Woodland Park forestry
agency had another $45,000 that was available for the same purpose.
Both granting systems required a Community Wildfire
Protection Plan as part of the application. Woodman said that his team had been
working on such a plan but had not yet completed it. He had discussed this with
both entities and they had suggested submitting preliminary plans prior to the
grant application closing date and then, later, follow up with the final plan.
Unlike previous grant applications, the money had to be allocated to specific
projects. The committee was working to come up with a suitable list with
emphasis on the extreme fire hazard present in areas around Fairplay Drive,
where there were extensive stands of thick scrub oak. The money could not be
moved around once allocated and required a 50 percent match from the entity
proposing the work.
From discussions with the two forestry departments, he
concluded that he would apply for a grant of up to $8,000 from the Woodland Park
agency and $10,000 from the state service. This was based on the chances of
receiving a grant based on the funds available, the number of people that were
applying for a grant, and the cost of relevant Woodmoor projects.
Woodman said this would mean the WIA board would have to
commit to corresponding funds in the grant application. He thought that the WIA
needed to make an effort to work on these grants so that both granting entities
would be aware that Woodmoor was an active player in wildfire protection
programs and interested in future grants. He said he thought that there was
already strong competition for these funds and only one in three applications
were successful.
He said he still needed to keep his current budget of $12,000
for tree cutting and common areas so that the matching funds would be in
addition to that.
Betty Hutchinson, treasurer, said that she thought that the
program was fiscally responsible because it would be a major benefit to the
whole community. Woodman said he would look to the Forestry Service and the
local Fire Department to identify projects to address the highest risk areas and
then have the costs estimated by a local forestry service company. The proposal
was approved unanimously.

August Weather Wrap
By Bill Kappel
Summer has continued to be wet and mild around the region as
more abundant moisture soaked the Tri-Lakes for much of August. So far this snow
season, which begins on July 1 and ends on June 30, we have received over 8
inches of rainfall, far ahead of normal and the most in that time period in at
least the past four years. With the numerous days of afternoon and evening
thunderstorms, temperatures have remained at or below average on many
afternoons. In fact, no heat waves were felt this month, as highs stayed below
90 every day.
August started off the way most of us had hoped, seasonal to
slightly below average temperatures and scattered thunderstorms. Six out of the
first seven days of the month saw high temperatures hold in the 70s, with 81°F
reached on the afternoon of the 4th. Soaking rains fell during the afternoons of
the 1st and 2nd, then again during the afternoon and evenings of the 6th and
7th. Once again we were fortunate to escape without having to deal with any
severe weather.
The second week of August was much like the first with
seasonal temperatures and scattered afternoon and evening thunderstorms. Highs
ranged from the mid 70’s to the low 80’s for the week. Accumulating rain
fell on the 7th, 8th, and 9th, then again on the 11th and 12th. Pretty much a
repeat performance occurred during the third week of August, as temperatures
stayed at seasonal levels and several rounds of thunderstorms rumbled through
the region. Rains fell hard and heavy during the evenings of the 19th and 20th,
with some small hail reported as well. Highs started off cooler than normal,
holding in the upper 60s on the 15th, then bouncing back to the upper 70s and
low 80s through the end of the week, before a cold front ushered in clouds and
cooler temperatures for Saturday. In fact, highs on Saturday struggled to reach
the mid-60s, and this was accompanied by fog and rain.
During the last weekend of the month, an unseasonably strong
low-pressure system moved through the region and brought with it several rounds
of strong to severe thunderstorms. These produced more heavy rain at times on
the 25th and 26th and included some hail. This system contained some pretty cool
air for this time of the year as well, and this helped generate severe weather
along parts of the Front Range and a dusting of snow above timberline. Pueblo
was hit hardest with this storm, as severe weather produced a tornado, damaging
winds, hail, and flash flooding.
The weather returned to normal for the last few days of the
month, as temperatures climbed back into the low 80’s on the 30th and 31st
under mostly sunny skies.
A look ahead
September is a transition month for the Tri-Lakes region,
with the last tastes of summer mixed in with our first morning freezes. Leaves
begin to change as well, and two out of the past three Septembers have seen at
least a trace of snow. The overall weather pattern is generally one of
tranquility, with our chances for thunderstorms dwindling and blizzard
conditions not quite ready for prime time. We are often greeted with sunny,
pleasant afternoons, with highs from the mid-70s early in the month to the
mid-60s later in the month. Our first sub-freezing low temperature usually
occurs during the second or third week as well, so prepare those plants.
The official monthly forecast for September 2005, produced by
the Climate Prediction Center (http://www.cpc.ncep.noaa.gov/products/predictions/30day/),
is calling for better than normal chances of above normal temperatures and equal
chances of normal precipitation. For a complete look at monthly climate
summaries for the Tri-Lakes region, please visit http://users.adelphia.net/~billkappel/ClimateSummary.htm.
August 2006 Weather Statistics
Average High 76.5°
Average Low 51.0°
Highest Temperature 86° on the 9th
Lowest Temperature 39° on the 28th
Monthly Precipitation 3.17"
Monthly Snowfall 0.0"
Season to Date Snow 0.0" (the snow season is from July 1 to June 30)
Season to Date Precip. 8.29" (the precip season is from July 1 to June 30)
For more detailed weather information and Climatology of the
Palmer Divide and Tri-Lakes region, please visit Bill Kappel’s Weather Web
page at http://users.adelphia.net/~billkappel/Weather.htm.
Remember, weather affects all of us every day and is a very
important part of life for us in the Tri-Lakes region. We want to hear from you.
If you see a unique weather event or have a weather question, please contact us
at our_community_news@hotmail.com.
Bill Kappel is a meteorologist and Tri-Lakes resident.

Letters to Our Community
Fishing with Jimmy and Mike
Recently at a Colorado Springs MDA fundraising event,
Monument firefighter Mike Rauenzahn and 13-year-old Jimmy Johnson met and talked
about things they have in common. Mike is a young, extremely strong professional
firefighter in the Tri-Lakes Monument Fire Department and a member of IAFF local
4319. Jimmy is bright, intelligent, outgoing and not afraid to roll up to Mike
in his wheelchair and start a conversation. After awhile the two found something
in common: they both like to fish. Mike had called Jimmy’s family a few days
after the MDA event to let them know he had developed some pictures of himself
and Jimmy at the Chili Cook Off MDA fundraiser.
Mrs. Johnson let Mike know that Jimmy was ready to go fishing
anytime he was available. Not only did Mike accept the invitation, he contacted
his fellow firefighters from Tri-Lakes Monument Fire Department, Members of
Donald Wescott Fire Department and El Paso County Search and Rescue. All
accepted the invitation to go fishing at Monument Lake, in Monument.
Mike did not stop there. He called the local Safeway and
asked them if they could supply lunch. They are donating hotdogs; buns,
condiments, soda and water for all that attend. Then Mike thought it would be
nice to set Jimmy up with some new fishing gear and tackle. Mike called a
manager at a local Wal-Mart, who donated a new fishing rod and tackle.
Mike is an exceptional member of our union, fire department,
and community. He wants to make this an event that can accommodate more members
of MDA next year with more sponsors. Mike has made a friend; Jimmy gets to fish
with a great guy. It’s nice to hear a "feel-good story."
Jody Thorpe
Local 4319 President

The return of eminent domain
Recently there was much concern about the District 38 School
Board invoking eminent domain. It was in the news often with a possible
"recall the board" campaign mentioned. Because of this, the school
board decided to choose a different set of properties to purchase. They did not
pursue due diligence and have ended up with an eminent domain decision again.
One of the properties being purchased is in the
covenant-restricted Williams Ranch subdivision. A search on the El Paso County
clerk and recorder site will show this— http://car2.elpasoco.com/rcdqueryhelp.asp.
The covenants are public record, if you wish to verify. The covenants preclude
the school board from using the property as they wish unless they invoke eminent
domain.
Here is what is ironic. The properties of the Williams Ranch
subdivision are currently owned by the children of the late Marion E. (Sandy)
Williams. Sandy Williams owned a ranch in the 1940s through the late 1960s, and
his neighbor was the Wissler Ranch, which the school board decided not to
eminent domain. Mr. Williams sold most of his property in the late 1960s, which
later became Woodmoor.
A letter from our attorney is being sent to inform the school
district of the decision they have to make. The Williams Ranch subdivision was
set up with covenants to protect the living quality of all the property owners.
Using eminent domain on one owner affects the lives of all in the subdivision.
Bob Patha

Between The Covers at the Covered Treasures
Bookstore: Page turners
By the staff of Covered Treasures
Looking for a couple of nonfiction "page turners"
for the end of summer? Colorado author and Denver Post senior columnist Dick
Kreck has just the answer. Kreck will sign two of his fascinating true-crime
tales at Covered Treasures during Art Hop from 5 to 8 p.m. Sept. 21.
Murder at the Brown Palace
By Dick Kreck, $17.95
Crimes of passion ruin lives in this tragic, true story set
in our state’s capital. Denver’s grand old hotel, the Brown Palace, is at
the center of this riveting drama that involves high society, adultery, murder
and drugs. The true characters in this book could not have been better cast.
Kreck’s research is excellent, and his story-telling skills make this a book
that will keep readers engaged from beginning to end!
Anton Woode: Boy Murderer
By Dick Kreck, $15.95
Kreck’s work combines a fascinating true-crime story with a
critical look at the criminal justice system of yesterday and its implications
for today.
Anton Woode was a baby-faced, 11-year-old boy accused of
shooting a man in the back in Colorado in 1892. As journalist Kreck tells the
riveting story of Woode’s controversial trial, harsh prison life and diligent
efforts at rehabilitation, he weaves in a well-researched history of the
criminal justice system and the Colorado figures that shaped it for better and
worse.
Want more regional, compelling history books? Check out the
following.
The Southwestern Journals of Zebulon Pike 1806-1807
Edited by Stephen Harding Hart and Archer Butler Hulbert, $27.95
This University of New Mexico Press reprint of Zebulon Pike’s
journal was released in conjunction with the bicentennial of Pike’s journey to
explore the headwaters of the Arkansas and Red Rivers. Throughout the
assignment, Pike kept a meticulous journal of his progress with descriptions of
the vast landscape, Indian tribes, and the daily events of the days’ travels.
Pike and his fellow explorers were captured in what is now southern Colorado and
brought to Santa Fe, N.M., where his journal was taken from him and was not
uncovered until the early 20th century. Hart and Hulbert provide commentary to
accompany the journal entries. A fascinating read for all who wonder about the
man whose mountain is the most famous in the land.

A Lady’s Life in the Rocky Mountains
By Isabella L. Bird, $8.95
Isabella’s letters to her loving sister are recorded in
this volume of the Western Frontier Library. Isabella is making her return trip
to her home in England and decides to tour the Rocky Mountain area of the
Colorado Territory. A young woman traveling alone on horseback was quite a
phenomenon in the late 1900s. She found the terrain daunting but invigorating
and incredibly beautiful. She described the area as "no region for tourists
and women" but might be amazed today at how things have changed.
Helen Hunt Jackson: Selected Colorado Writings
Edited by Mark I. West, $12.95
Helen Hunt came to the Colorado Territory in 1873 due to
failing health. The fresh air led to a recovery. Reluctant to come so far from
her New England home, she was pleasantly surprised at the awesome beauty
surrounding her, and in her writings she is an avid advocate of Colorado. Many
of us have moved here from other areas of the country and can relate to her love
affair with such a beautiful state. Reading this book of writings will just
emphasize our desires to keep Colorado as pristine as possible.
As summer draws to a close, many readers seek meatier books,
whether they are literary novels, political books, current affairs or historical
books. Colorado history is alive with fascinating characters and amazing feats.
Enjoy reading, and visit here again next month!

High Country Highlights: To Deadhead or
Not to Deadhead
By Woody Woodworth
Increase the enjoyment and value of your flowering plants by
investigating the potential of deadheading. The process of removing the
faded/spent flowers before they set seed with the goal of forcing a plant to
rebloom is called deadheading. Some say deadheading is a way of fooling Mother
Nature. To decide if deadheading is right for your flowers, consider the normal
life cycle of a flowering plant, the goal of deadheading and the proper
techniques to follow.
If left alone, a flowering plant would put forth a bloom. The
blossom would then be fertilized and set seed. In this complete reproduction
task, the plant expends its energy and nutrients to set seed instead of
producing more flowers. Annuals are intended to grow, flower, set seed and die.
The main goal of deadheading is to produce more blooms on a
plant. This goal extends the value of your investment on annuals and perennials,
and beautifies your flower gardens by removing the dried-up flowers. In
addition, deadheading your flowering plants conserves plant energy and removes
hiding places and food for insects that often become pests in our gardens. It
can also reduce the potential for fungal diseases by permitting minor
improvements in air circulation.
Not all plants will bloom a second time even after
deadheading them (e.g., poppies). You still may want to snap off the spent
blooms to save the plant’s energy, to make the plants look neater and to help
the plant be stronger and produce nicer blooms the next season.
Deadheading plants is not difficult. You’ll want to plan to
remove the seed head before the seeds start to develop—before the florets
begin to fall. Snap off any faded or dead flowers between the fingers and thumb.
Make sure the stems are broken cleanly. If the stems are tough or if there is
danger of hurting the plant as the dead flowers are removed, you may want to use
scissors, pruners or a penknife. For plants that get long and gangly, like the
blue salvia, you want to cut the entire plant back in half. While it will look
"bald" at first, the new growth will rush right out and fill it in.
Fortunately, some annuals, such as begonias and impatiens,
are "self-cleaning." They drop their spent flowers and continue to
bloom for a long season. Impatiens naturally get leggy when it is hot and wet.
These plants benefit by being cut back in half.
While deadheading roses, keep in mind that a bloom stem can
be no larger in diameter than the stem from which it grows. Thus, the subsequent
blooms will be proportionate in size to the stem from which they emerge. This
means the further down the stem you cut, the larger the bloom stem and
subsequent buds will become. Keep in mind that the larger the bloom stem, the
longer it will take for the rose to rebloom. Make your cut at an angle away from
and slightly above the node.
No matter what kind of plant you are working on, do not
remove any foliage, even if it starts yellowing. The nutrients for next year’s
blooms are still being transported to the roots at this stage.
While deadheading your flowering plants may be a way of
fooling Mother Nature, it is also a way to give your garden a longer blooming
season. It does not appear to hurt your plants. In fact, it conserves their
energy and often provides stronger more beautiful plants the following season.

Reflections: A Care Bear Color
Wheel
By Judith Pettibone
I finished stuffing the oval rainbow tummy I had stitched
onto a pair of pink-footed jammies turned backward. I felt a surge of pride at
the thought of my 3½-year-old showing up at her preschool Halloween party as
"Cheer Bear," the pink rainbow Care Bear. After cutting off the feet
and crafting a wee plush hood with ears, she would be the Care Bear she had
requested. Voila! I may even have giggled.
That was 21 years ago, and my now 24-year-old daughter
remembers this costume as her "favorite"!
What she has no memory of, except in my telling— which has
grown to fable proportions— is what happened the day of the preschool
Halloween party.
In the car, the excitement is palpable. Our little
preschooler has become what she cherished—a rather worn stuffed animal who
accompanies her to all cuddling occasions. She, naturally, never notices the
worn part. And one surely would not describe her costume, thus. It was just
plain darling … until ….
Words are insufficient to describe what emotions probably
crossed my face as I saw one of the other little darlings walk in. Not only was
she also a Cheer Bear, she had just popped off the Toys R Us shelf—an ACTUAL
Cheer Bear. Her pink velvet body (no backward jammies for this missy) and a
fully tucked, stitched and sculpted, identical version of the head of the Bear
my daughter carried to bed, was a vision. If it hadn’t been so astonishing, I
would have been amazed that anyone—grandma or other—could hand-make such a
creation.
Flash forward to yesterday. My youngest daughter has left her
comfort zone at Colorado State University and is attending a professional
fashion school in Los Angeles. Although artistic, she is not an artist—at
least not yet.
Her first rigorous assignment in a color and design class
(where, according to the prof, "perfection is possible") was to create
her own color wheel—mixing the paints and incorporating a design element. Ten—10!—hours
later, she e-mailed us a photo of a very handsome color wheel using the 12
astrological signs. At least, it sure looked handsome to us.
I really did think it looked terrific, amazing even. And
then, unbidden, a phrase popped into my head—"Sure hope there aren’t
any ‘Care Bear Color Wheels’ in her class."
Just as I’m pretty sure I never made another
"realistic" Halloween costume, I’m wondering what else I haven’t
tried. How many of our attempts end before they begin? Because of the Care Bear
Poem in third grade, or the Care Bear Dessert at the potluck or even the Care
Bear team, was the burgeoning poet, baker or athlete discouraged?
We each have our special talents. It’s when we try
something new and feel awkward that those internal and external comparisons may
make us cringe. I am heartened by the fact that my daughter, out on a new limb,
did not seem the least bit intimidated by what she thought the others might
bring to the table. Comparing oneself only to oneself could lead us down paths
we otherwise may not have traveled.
If someone wants to teach a class in "Sculpting Your
Basic Care Bear Costume Head," count me in.

Bird Watch on the Palmer Divide: Yellow
Warblers
Drawing by Elizabeth Hacker
Click here or on the drawing to zoom in

By Elizabeth Hacker
August is prime time for bird watchers. Early one morning,
Randy and I observed bluebirds in Castlewood Canyon State Park teaching their
fledglings how to forage for food. As the day warmed, the raptors began to soar
on the thermal air currents, at which time the songbirds ceased their activity
and hid in the shadows of trees to avoid becoming a meal. We also observed a
great blue heron teaching an adolescent heron to fish in Palmer Lake. Although
the adolescent was the same size as its parent, it did not yet have the
distinctive plumage or graceful movement of its parent.
Fellow birder Jean Anderson of Palmer Lake reported seeing a
double-crested cormorant. In my search for it, I observed a pair of yellow
warblers nesting in a willow. This was somewhat surprising to me because while
we previously spotted them migrating through here earlier this summer in Fox Run
Park, we had never observed warblers nesting here. That is not to say that they
don’t; we just haven’t seen them.
The yellow warbler is the most striking member of the wood
warblers or New World warbler family that includes many species that annually
migrate between Central and North America. Wood warblers are generally small
sparrow-sized perching birds with a big song, but they vary quite a bit in
appearance. This family of birds is cherished in many communities. In some
states, various warbler species have been designated as the state bird.
The yellow warbler is a little bird, about 6 inches in
length, which moves so quickly that until recently, I often misidentified it as
a goldfinch. At first glance, it appeared as a flash of bright yellow darting
from one tree branch to another. Unlike the goldfinch, it has no distinguishing
black markings. In summer, the male is olive-green above and a brighter yellow
below. With a good pair of binoculars, one can observe the copper-colored
streaks on its breast. The female is olive to brown all over. Other
distinguishing features include a small black beak and round eyes.
This summer was the first time we observed the yellow warbler
in more than one location. It is an insectivore but also eats berries and is
generally found near water or a wetland. This may explain why we’ve never seen
one at a feeder. In addition to seeing it near water, we also found it perched
in the top of a tall ponderosa pine in the Pike National Forest. The pair we
observed at Palmer Lake was busy moving between its nest in a willow tree and a
pile of old branches in search of insects to feed the nestlings, which were
calling out for more food. Unlike the sweet song of the parents, the nestlings’
annoying chirps would motivate any parent into action.
The biggest threat to the yellow warblers is the cowbird.
This native wanderer will lay one of its eggs in another bird’s nest.
Sometimes song birds will recognize and destroy a foreign egg or chick, but
often they don’t, and will raise it as if it were one of its own. Cowbird eggs
will generally hatch a day earlier than other eggs, and because the parent must
leave the nest to find food for it, the other eggs may not hatch. If they do
hatch, the cowbird chick grows faster and will dominate the clutch. This, in
addition to habitat loss, is thought to have reduced the warbler population in
the Western states.
We are happy to report that we finally spotted the elusive
blue grosbeak, but it was not where we expected it to be. In our research, we
had read that it perches in shrubs next to water. We found it on top of a tall
cottonwood tree quite a distance from the water. Maybe birds don’t always read
the bird books! We were only able to observe it from afar and then for only a
few minutes. So next summer we will look for it again. Hopefully, Santa will
reward us with a viewing scope so we can get a closer look at it earlier in the
season.
Elizabeth Hacker is an artist in the Tri-Lakes area. Her bird
prints are available at the gift shop in the Tri-Lakes Center for the Arts in
Palmer Lake. E-mail her with your questions and bird finds at OCN.

Art Matters: It pays to collect
art
Below: September Aspens by Sharon DeWeese (Buffalo Blues
Gallery)

By Janet Sellers
I stopped by the Winter Gallery’s Western Art Show recently
and was lucky to meet owner Steve Stingley as he talked to his friend, Kit
Haddock. I noticed Kit was dressed up in cowboy attire, boots to hat, and I
thought he was a cowboy artist in the show. Truly, Kit is exhibiting a large
watercolor painting, but it is from his personal art collection and the work is
by Denver artist William Matthews, considered in some circles to be the
"new Remington."
Kit told me that, as a collector, he considers a number of
things when investing in fine art. In the current painting for sale he has at
the gallery, he was attracted to the personal memory and moment of the branding
of the cattle. Years ago, he had gotten this watercolor at the Matthews Gallery
in Denver. He had seen the painting the day before Matthews’ art opening and
bought it on the spot. He reports it was a hot item at the actual show, but he
was the one who got to take it home. It has gone up quite a bit in value, and
although he has enjoyed it for some years, he will also enjoy selling it and
hunting for another artwork to add to his collection of Western art.
We talked for a bit about the collector’s viewpoint on
selling a painting via a gallery or auction. Kit mentioned that a friend had
bought a Western painting for some $65,000. And in a few years the painting was
resold to a celebrity in Santa Fe for something like $195,000.
This got me thinking about the secondary art market. The
artist’s works are generally bought at the greatest value on the dollar at the
earliest purchase moment—from the artist or from the primary art gallery.
After that, the price will go up and the value is on its way to increasing year
after year. Rare is the buyer or collector who tells the artist the painting isn’t
priced high enough, but wait until they go to resell the art work, and they are
sure to tell the gallery to up the price as high as possible. It is all in the
name of business. Artists, beware! Well, most artists know their primary market
value, or they should know it, as well as they should understand the growth
factors. It is not hard to learn, but there are certain details that go into the
pricing, regardless of genre.
Just what, exactly, influences the price and value in the
first decades, especially? According to museums, galleries, art fund advisors
and the art auction professionals, there are several critical influences to the
value, and therefore the price. Important factors include scholarship,
exhibition history, and "freshness to the market." This translates
basically into the factors of what the literati have to say, where the art has
been to "show off," who’s looked at it, who’s owned it, and if it
is fresh on the market. These attributes are usually recorded in detail, and
some even hold a title to the work with this data. All of these factors together
combine into an ongoing growth market for the art, and such details are
especially prized by the art collectors.
Well, speaking of fresh on the market, our community has a
lot of art for sale and art events to offer this fall, and here is a list of
events for September:
Brown Bag Saturdays at Buffalo Blues: Sharon DeWeese,
fine artist and owner of Buffalo Blues Gallery at 135 Second St., downtown
historic Monument, will be giving free watercolor demos noon to 1 p.m. Saturdays
in September. Begins Sept. 2: come inside, bring your brown bag lunch if you
want, and "watch a painting appear before your eyes." Please call
481-3720 to reserve a seat as space is limited.
Annual Member Artists Exhibit at Tri-Lakes Center for the
Arts: Sept. 2 through Oct. 20. A reception will be held on Sept. 8, from 5:30 to
8p.m. The Member Show is an event to showcase the 100-plus TLCA artist members.
The Center is open Wednesday through Saturday from noon to 4 p.m., 304 Highway
105, Palmer Lake, CO 80133, (719) 481-0475. A Silent Auction has been added to
the show benefiting TLCA. The auction will continue throughout the show with
winners notified after Oct. 20.
Tri-Lakes Center for the Arts is dedicated to creating
community partnerships for demonstrating, teaching, exhibiting and promoting the
arts and humanities. The Center is an advocate for artistic growth in the
community.
Monthly Art Hop in Monument: September Art hop is 5-8
p.m. Sept. 21. Historic Monument holds its monthly art event. Bring a friend and
stroll the town with art in mind. From Beacon Lite Road and Second Street on
West to Third Street, enjoy going out on the town for art’s sake.
Free After-Hours Art "Sampler": Bring a friend
and munch on biscotti while you visit an art evening for would-be
creatives, artists, collectors – every level of interest! Start your art
connection this season with the Monument School of Fine Arts at the monthly art
evening in September. Short, informal talks and tips on artists’ creative
secrets: preserving/protecting art, framing, and the why/how of art buying.
Professional artists will demonstrate techniques in several "Studio
Samplers" including digital photo, drawing, painting, sculpture and jewelry
making. We plan to have them monthly, and the September Art Sampler will meet at
the Monument Library on Sept. 26 from 6-8:30 p.m. Drop-in or RSVP: 488-8280

Over the Bar performs for
the Black Rose Acoustic Society, Aug. 25.
Photo by Cari Colvin


Special Events and Notices
By Judy Barnes, Editor Emeritus
Although we strive for accuracy in these listings, dates or
times are often changed after publication. Please double-check the time and
place of any event you wish to attend by calling the info number for that event.
Last Month for the Black Forest Slash-Mulch
Site
There’s still time to trim and thin your trees and take
your slash to the Black Forest Slash-Mulch Site. The site is a wildfire
mitigation and recycling program of the El Paso County Solid Waste Management
Department. You may bring slash up to 6 feet long and up to 8 inches in diameter
to the slash-mulch site, where it will be ground into mulch and recycled. The
site is located in Black Forest on the east side of Herring Road, between Shoup
Road on the north and Burgess Road on the south.
Slash will be accepted through Sept. 17, Tuesday and
Thursday evenings 5 to 7:30 p.m.; Saturdays, 7 a.m. to 4 p.m.; and Sundays, noon
to 4 p.m. The cost is a donation of nonperishable food for nonprofit Black
Forest organizations. No stumps, roots, lumber, railroad ties, dirt, weeds, or
household trash will be accepted. Loads must be covered and tied, and children
and pets must stay inside the vehicle while at the site.
Mulch will be available until Sept. 23. Bring your own
tools and load mulch free of charge. In September the mulch loader will be
available Saturdays, from 7 a.m. to 4 p.m. The loader fee is $4 per bucket.
For more information, call El Paso County Solid Waste
Management at 520-7878 or Ruth Ann Steele at 495-3107, or visit www.bfslash.org.

Cook a pot of Chili for Charity!
The Third Annual High Country Chili Cook-Off will take place
in Monument Sept. 16 at High Country Home & Garden, 243 Washington
St. The event is a benefit for Tri-Lakes Cares, a local charity and food pantry.
Cooks will set up at 7 a.m. and meet at 8:30 a.m. The red and green sample
turn-in time is 12:30 p.m., with awards given at 3 p.m. Chili must be cooked at
the Washington Street site from scratch with no fillers. Each cook may submit
only one chili sample. Washington Street will be closed from Second to Third
Street for through traffic. The deadline for entries is Sept. 12. Send
entry forms and fee to Colorado Chili Pod, c/o John Montgomery, 1670 Broadway,
Suite 3000, Denver, CO 80202. For more information, call Catherine at 481-3477.

County Citizens’ College
The El Paso County Citizen Outreach Group is still receiving
applications to attend the first annual El Paso County Citizens’ College.
Seven 4-hour sessions will be held one evening each week at various County
facilities Sept. 18 through Oct. 30. Classes are free of charge
thanks to private donations from community sponsors. The Citizen’s College
will give county residents the opportunity to meet government leaders, learn
about county programs and increase their knowledge of how our taxes are being
spent.
Additional information and application are available directly
from a link on the El Paso County web site at www.elpasoco.com.
Even though the due date has passed, you can still apply. If interested, phone
Joe Salute, 495-4686.

Community Meeting on Second High School
Site
The community is invited to a meeting Sept. 19, 7
p.m., about a new D-38 high school planned for land north of Lewis-Palmer middle
school between Woodmoor Drive and Monument Hill Road, in the general area of
Hunter Run Farm. The meeting will be at the Monument Branch Library, 1706 Lake
Woodmoor Dr. For more information, contact Nancy at 591-0506 or 487-8754.

Octoberfest at TLCA
Celebrate Octoberfest at Tri-Lakes Center for the Arts (TLCA)
Sept. 30, 6:30 to 10 p.m. Enjoy Octoberfest beer with traditional
Octoberfest food, and live music with an Octoberfest flavor. A special beer
tasting will feature specialty beers paired with foods. The entry ticket, $25
for members and $30 for non-members, will include five tickets for beer and
food, with more available for purchase. TLCA is located in the historic Kaiser
Frazer building at 304 Highway 105, Palmer Lake. For more information, call
481-0475.

Wine & Roses coming in October
Tri-Lakes Women’s Club’s annual wine tasting benefit will
be held Oct. 20, 6-9 p.m., at The Inn at Palmer Divide in Palmer Lake.
Celebrity wine servers will be pouring dozens of fine wines to enjoy with hors d’oeuvres
and a silent auction. Tickets are $40 in advance and $45 at the door. Visit the
Web site, www.tlwc.net, or phone
551-1946. Tri-Lakes Women’s Club benefits local nonprofit groups such as
District 38 schools, fire and police departments, senior citizen groups, and
other nonprofit 501(c)(3) organizations that provide services to residents
within the community.

Wildlife Masters in El Paso County
Do you wonder how to keep the deer from munching your freshly
planted garden, how to get the skunk out from under your deck without getting
sprayed, or how to get the squirrels out of the attic? Colorado State University
Cooperative Extension in El Paso County has a staff of trained Wildlife Masters
to help you. Call the Master Gardener Help Desk, 636-8921, and you will be
called promptly with an answer. A fact sheet will be sent to you by e-mail or
regular mail. For more information, call 636-8921 or e-mail csumg2@elpasoco.com.

Lewis Palmer High School Serteen Club
wins Club of the Year Award for the third time
Below: The Lewis Palmer High School Serteen Club was
once again the winner of the Sertoma International Serteen Club of the Year
Award. The LPHS Serteen Club was presented with the award at the Sertoma
International Conference held in Omaha, Nebraska, in July. This is the second
year in a row the club has won the award and the third time in five years. The
application process for the award is lengthy and closely examined for club
activities, cumulative club community service hours, and club member
participation. Pictured left to right: Max Williams, Monument Hill Sertoma
Serteen Advisor; Cameron Barton, LPHS Serteen President 2006, and Ron Pitt,
Monument Hill Sertoma President. Photo and caption provided by Eddie Kinney


|